NCLT Hyd. (2026.02.24) in Mark Infrastructure Pvt. Ltd. vs NBCC India ltd. and Anr. [(2026) ibclaw.in 571 NCLT, IA No 109 of 2023 in CP (IB) No. 14/9/HDB/2021] held that;-.
Section 14(3)(b) of the IBC clearly provides that the moratorium shall not apply to a surety in a contract of guarantee to a Corporate Debtor. Further, the proviso to Section 3(31) excludes performance guarantees from the ambit of “security interest.” A conjoint reading of the aforesaid provisions makes it clear that a Performance Bank Guarantee stands outside the purview of moratorium under Section 14. Therefore, invocation of the Performance Bank Guarantee by Respondent No.1 cannot be held to be illegal or in violation of the provisions of the Code.
Admittedly, the project was not completed by the Corporate Debtor. The retention, being contractual in nature, cannot be directed to be refunded unless the contractual conditions are fulfilled. This Adjudicating Authority, exercising jurisdiction under Section 60(5), cannot rewrite the terms of the contract between the parties.
It is well settled that this Adjudicating Authority, under Section 60(5) of the IBC, is not empowered to adjudicate purely contractual disputes unrelated to insolvency resolution. The jurisdiction under the Code is confined to matters arising out of or in relation to the insolvency of the Corporate Debtor. Determination of delay compensation, entitlement under RA bills, and consequences of contractual breach fall within the realm of contractual adjudication and cannot be conclusively determined in summary proceedings under the IBC.
In view of the foregoing discussion, we are of the considered opinion that the invocation of the Performance Bank Guarantee does not violate Section 14 of the IBC and the retention amount and deductions from RA bills are governed by contractual terms and cannot be directed to be refunded in the present proceedings. Further the disputes raised are predominantly contractual in nature and do not warrant interference under Section 60(5) of the Code.
Excerpts of the Order;
# 1. This application is filed by the Resolution Professional of Mark Infrastructure Pvt Ltd under Section 60 (5) of IBC, 2016, r/w Rule 11 of NCLT Rules, 2016, seeking directions to Respondent No.1 to refund/ pay a sum of Rs. 6,15,49,971/- to the Corporate Debtor.
AVERMENTS IN THE APPLICATION:
# 2. The Tribunal had earlier initiated the Corporate Insolvency Resolution Process (CIRP) against the Corporate Debtor vide order dated 30.12.2021 and appointed Mr. Ritesh Mittal as Interim Resolution Professional, who was subsequently replaced by Mr. Venu Gopal Kaspa and subsequently by Mr. Madasa Kumar as Resolution Professional.
# 3. It is stated that the Corporate Debtor, an MSME, had entered into a contract agreement with Respondent No. 1 for the construction of the remaining portion of the new campus for the National Institute of Design (NID), Vijayawada, Andhra Pradesh, at a contract value of approximately Rs. 44.70 crores.
# 4. In terms of the contract, the Corporate Debtor had furnished a Performance Bank Guarantee (PBG) issued by Punjab National Bank, vide BG No. 06871LG000319, for a sum of Rs. 2,23,48,322/- dated 07.01.2019, representing 5% of the bid value, to secure the due performance of contractual obligations.
# 5. It is stated that the Respondents No.1 and 2 retained 2.5% of each running account bill as retention money towards the Defect Liability Period (DLP) and released the balance payment for the work executed. Accordingly, a total sum of Rs. 1,49,07,328/- was retained by the Respondent No.1 from 22.03.2019 to 17.12.2021 under the DLP provisions.
# 6. The Applicant has detailed the total funds available with Respondent No.1 belonging to the Corporate Debtor, which amounts to Rs. 6,15,49,971/-, as under:
# 7. The grievance of the Applicant is that, despite the Corporate Debtor having executed approximately 95% of the work allotted under the contract satisfactorily, the Respondents, without considering the exceptional circumstances arising due to the COVID-19 pandemic, allegedly withheld payments for the work completed, and further threatened to cancel the contract and invoke the Performance Bank Guarantee (PBG) furnished by the Corporate Debtor.
# 8. Aggrieved by the actions of the Respondents, the Resolution Professional (RP), on behalf of the Corporate Debtor, filed IA 279/2022 against Respondents No.1 and 2, seeking the following reliefs:
(a) To release the payment of pending invoices and amounts held by the Respondents in the running account bills, amounting to Rs. 2.43 crores, to the Corporate Debtor, since the funds of the Corporate Debtor with the Respondents are assets of the Corporate Debtor under the CIRP.
(b) To pass an order directing the Respondents to release the Performance Bank Guarantee (PBG) of Rs. 2.23 crores, since an amount of Rs. 1.49 crores is already retained as security deposit, which exceeds 3% of the contract value, in accordance with the Ministry of Finance, Government of India, Office Memorandum dated 12.11.2020.
(c) To pass an order directing the Respondent No.1 to cooperate with the CD in completing the balance meagre work for smooth running of the business of the CD during the pendency of CIRP as the Civil Court has no jurisdiction in respect of the matters connected with the CD under CIRP as per the I&B Code.
a. To pass such order/orders as this Hon’ble Tribunal may deem fit and proper in the circumstances of the case in the interest of justice and equity
Interim Relief: Pending disposal of IA 279/2022, the RP sought an interim injunction restraining the Respondents or their officers/agents from invoking PBG No. 06871LG000319 dated 07.01.2019 for Rs. 2,23,48,322/-, and restraining Punjab National Bank from making any payment to Respondent No.1 in respect of the said PBG.
This Tribunal after careful consideration of the entire material before it, passed a detailed order in IA 279/2022 dtd. 08.06.2022, but the Respondents have willfully and deliberately failed to:
(1) release the 25% amount from the 2% excess PBG amount as directed by this Hon’ble Adjudicating Authority;
(2) issue to the Form III, a statutory requirement for the Applicant to get the labour license before initiating the work;
(3) furnish the work schedule;
# 9. According to the Applicant, the Respondents, with an intention to gain time and to ensure that the Corporate Debtor did not complete the work within the three months as directed by this Adjudicating Authority, filed an appeal on 12.07.2022 before the Hon’ble National Company Law Appellate Tribunal against the order dated 08.06.2022 passed in IA 279/2022.It is further contended that the said appeal was subsequently withdrawn on 18.08.2022 before the Hon’ble Appellate Authority without assigning any reasons. Thereafter, immediately upon expiry of the three-month period, Respondent No.1 issued a termination letter dated 07.09.2022 to the Corporate Debtor.
# 10. The Applicant submits that pursuant to the order dated 08.06.2022 in IA 279/2022, it filed an undertaking affidavit on 15.06.2022 agreeing to complete the project within the time granted by this Adjudicating Authority, while requesting Respondent No.1 to fulfil certain reciprocal obligations necessary for commencement and smooth execution of the work. It is stated that time was the essence of the contract and the extended period had expired on 31.03.2022. Although the agreement dated 29.01.2019 permits recovery of delay compensation, Respondent No.1 had repeatedly modified and enlarged the scope of work and granted extensions, the last being on 29.10.2021 with time extended up to 31.03.2022. Apprehending recovery of delay compensation beyond 31.03.2022, the Applicant sought an unconditional extension of time in line with the order in IA 279/2022 and issuance of Form III for obtaining a labour licence, as conditions necessary to safeguard the interests of the Corporate Debtor.
# 11. The Applicant further undertook to commence the work forthwith, complete the works required for temporary functioning of the campus within 30 days, and finish the remaining work within three months from the date of undertaking. It also sought release of 25% from the 2% excess Performance Bank Guarantee amount to facilitate execution of the temporary works. Despite expressing readiness to complete the project, Respondent No.1 terminated the contract vide letter dated 07.09.2022.
# 12. Aggrieved by the aforesaid actions, the Applicant filed Contempt Petition No. 05/2022 before this Adjudicating Authority on 24.09.2022 and also instituted W.P. No. 36674 of 2022 before the Hon’ble High Court of Andhra Pradesh. By order dated 11.11.2022, the Hon’ble High Court held that the termination dated 07.09.2022 was contrary to the orders of this Adjudicating Authority and accordingly suspended the termination. Subsequently, on an application filed by the Respondents seeking vacation of the interim order, the Hon’ble High Court, by order dated 06.01.2023, vacated the stay granted on 11.11.2022.
# 13. The Applicant submits that although Respondent No.1 granted extension of time up to 30.03.2022, the Corporate Debtor was admitted into CIRP on the same date. Thereafter, the Respondents allegedly turned hostile, withheld payments even for certified works, and invoked the performance bank guarantee, thereby causing serious financial prejudice to the Corporate Debtor. The Applicant contends that such withholding of amounts due to the Corporate Debtor is unjust and illegal. Given that the Corporate Debtor is undergoing CIRP, retention of these funds would result in value erosion and defeat the fundamental objective of the Code, namely maximization of value and balancing the interests of all stakeholders.
COUNTER:-
# 14. The preliminary objection raised by Respondent No. 1 is that due to failure of the Corporate Debtor to perform its contractual obligations, the Performance Bank Guarantee was invoked strictly in accordance with due procedure. Further contention of Respondent No.1 is that invocation of a Performance Bank Guarantee is not barred by the moratorium under Section 14 of the Insolvency and Bankruptcy Code, 2016, as Section 14(3)(b) excludes guarantees given to a Corporate Debtor, and the proviso to Section 3(31) expressly excludes performance guarantees from the definition of “security interest.” A conjoint reading of these provisions, according to the Respondent, clearly places Performance Bank Guarantees outside the purview of moratorium.
# 15. The Respondent further submits that no amounts are due to the Corporate Debtor. The retained sums pertain to defect liability and non-achievement of contractual milestones, and have been withheld strictly in terms of the agreement. Owing to persistent delays and poor performance, despite time being the essence of the contract under Clause 3.4 of the Agreement dated 29.01.2019, the Respondent had already terminated part of the works on 23.12.2021, prior to commencement of CIRP. As the project relating to the National Institute of Design, Vijayawada was required to commence operations in July 2022, and the Corporate Debtor failed to complete the works even after substantial delay, the Respondent was compelled to terminate the contract and engage third parties to complete the balance work.
BRIEF FACTS AS NARRATED BY RESPONDENT No.1 IN THE COUNTER
# 16. That Respondent No. 1 invited tenders vide NIT No. NBCC/CPG/ NID/Vijayawada/ 2018/165 dated 10.09.2018 for construction of balance works of National Institute of Design (NID), Vijayawada, on behalf of the Department of Industrial Policy and Promotion, New Delhi. The Corporate Debtor was awarded the contract valued at Rs. 44,69,66,450/- vide Letter of Award dated 27.11.2018, with an 8-month completion deadline (by 06.08.2019).
# 17. It is stated that when the Corporate Debtor failed to complete the project despite being granted multiple extensions, Respondent No. 1 issued several notices highlighting slow progress and non-adherence to revised schedules, including show cause notices dated 18.02.2021, 16.10.2021, 01.11.2021, 26.11.2021 and 09.12.2021. Owing to continued non-performance, Respondent No. 1 partly withdrew the scope of work on 23.12.2021. Further notices were issued over expired labour licence and workman’s compensation insurance, leading to issuance of another show cause notice dated 05.03.2022 following which the Performance Bank Guarantee was encashed on 25.03.2022.
# 18. It is further stated that the Corporate Debtor sought injunction vide IA No. 279/2022, against termination and release of payments. But upon failure to comply with this Tribunal’s conditional order dated 08.06.2022 to complete essential works within 30 days, NBCC issued a termination letter on 07.09.2022. The Corporate Debtor challenged this before the Andhra Pradesh High Court (W.P. No. 36674/2022), which, after initially granting an ex parte stay, ultimately upheld the termination and vacated the stay. Hon’ble High Court, after hearing, upheld the validity of the termination and vacated the interim stay.
PARA-WISE REBUTTAL BY RESPONDENT NO.1
# 19. It is stated that Paras 1–4 and 7 are matters of record and require no specific reply. The claims in Para 5 are denied as false and untenable, as any payment is contingent upon completion of contractual works, which according to Respondent No.1, the Corporate Debtor failed to achieve.
# 20. It is stated that the Retention Amount of Rs. 1,49,07,328/- was deducted as security deposit/retention money under Clause 3 of General Conditions of Contract GCC, refundable only after the defect liability period. Since the project was incomplete, according to R-1, no refund is due.
# 21. It is further stated that the Performance Bank Guarantee of Rs. 2,23,48,322/- was lawfully invoked on 25.03.2022 for non-performance and that its invocation is not hit by moratorium under Section 14 of IBC, in view of Section 14(3)(b) and Section 3(31), which exclude guarantees from the purview of moratorium.
# 22. The claim of Rs. 2,42,94,321/- towards pending RA bills is denied and contends that the deductions were made towards delay compensation under Clause 3 of the Special Conditions of Contract SCC (@0.5% per week). Further, RA Bill–31 dated 07.01.2022 was signed post-CIRP initiation by the previous management’s GPA holder, rendering it void. According to Respondent No.1, under Clause 23.1 of the GCC, running bills are only advance payments and do not signify completion or acceptance of work.
# 23. It is contended that quantity variations were disclosed in the tender and consented to by the Corporate Debtor. The COVID defence is rejected, as the original completion date was 06.08.2019, well before the pandemic.
# 24. It is stated that regarding the Order dated 08.06.2022, the undertaking filed was not unconditional and failed to address completion timelines for WTP, STP, and plumbing works. The Tribunal noted non-compliance on 21.06.2022, enabling Respondent No. 1 to invoke Clause 11 of GCC and terminate the contract on 07.09.2022, subsequently upheld by the Andhra Pradesh High Court.
# 25. The allegations in Paras 12–17 are denied by Respondent No.1 and submits that all retentions and deductions were done strictly as per contractual terms, and no amounts are due to the Corporate Debtor.
# 26. We have heard the Learned Counsel appearing for the Applicant/Resolution Professional and the Learned Counsel for Respondent No.1. We have perused the pleadings, documents placed on record, and the earlier orders passed by this Adjudicating Authority in IA No. 279/2022.
# 27. The present Application has been filed under Section 60(5) of the Insolvency and Bankruptcy Code, 2016 seeking directions to Respondent No.1 to refund/pay a total sum of Rs. 6,15,49,971/-, comprising alleged pending RA bills, retention money, and the amount covered under the Performance Bank Guarantee.
# 28. The principal issues that arise for consideration are:
(1) Whether the invocation of the Performance Bank Guarantee amounting to Rs. 2,23,48,322/- is barred by the moratorium under Section 14 of the IBC, 2016?
(2) Whether the retention amount and deductions from RA bills are liable to be released to the Corporate Debtor during CIRP?
ISSUE (1)
# 29. The Applicant contends that invocation of the PBG constitutes an action against the assets of the Corporate Debtor and is therefore hit by the moratorium. The Respondent No. 1, however, relies upon Section 14(3)(b) of the IBC and the proviso to Section 3(31), contending that performance guarantees are expressly excluded from the definition of “security interest” and are therefore outside the purview of moratorium.
# 30. Insofar as the Performance Bank Guarantee is concerned, it is an undisputed fact that the same was invoked on 25.03.2022. Section 14(3)(b) of the IBC clearly provides that the moratorium shall not apply to a surety in a contract of guarantee to a Corporate Debtor. Further, the proviso to Section 3(31) excludes performance guarantees from the ambit of “security interest.” A conjoint reading of the aforesaid provisions makes it clear that a Performance Bank Guarantee stands outside the purview of moratorium under Section 14. Therefore, invocation of the Performance Bank Guarantee by Respondent No.1 cannot be held to be illegal or in violation of the provisions of the Code.
ISSUE (2)
# 31. With regard to the retention amount of Rs.1,49,07,328/-, the same was deducted in terms of Clause 3 of the General Conditions of Contract towards security deposit/retention money, refundable only upon completion of the defect liability period. Admittedly, the project was not completed by the Corporate Debtor. The retention, being contractual in nature, cannot be directed to be refunded unless the contractual conditions are fulfilled. This Adjudicating Authority, exercising jurisdiction under Section 60(5), cannot rewrite the terms of the contract between the parties.
# 32. Further, as regards the claim of Rs. 2,42,94,321/- towards pending RA bills, Respondent No.1 has contended that the amounts were deducted towards delay compensation under the Special Conditions of Contract and that running account bills do not constitute final acceptance of work, as per Clause 23.1 of the GCC. The material placed on record indicates that the project suffered substantial delay, and part termination had already taken place prior to initiation of CIRP. The disputes raised pertain essentially to contractual performance, delay, and computation of payable amounts, which are matters requiring adjudication on evidence and interpretation of contractual clauses.
# 33. It is well settled that this Adjudicating Authority, under Section 60(5) of the IBC, is not empowered to adjudicate purely contractual disputes unrelated to insolvency resolution. The jurisdiction under the Code is confined to matters arising out of or in relation to the insolvency of the Corporate Debtor. Determination of delay compensation, entitlement under RA bills, and consequences of contractual breach fall within the realm of contractual adjudication and cannot be conclusively determined in summary proceedings under the IBC.
# 34. We further noted that pursuant to the earlier order dated 08.06.2022 in IA No. 279/2022, the Applicant was directed to file an unconditional undertaking to complete essential works within the stipulated time. The record reflects that the undertaking furnished was found non-compliant, and Respondent No.1 thereafter proceeded to terminate the contract on 07.09.2022. The said termination was subsequently upheld by the Hon’ble High Court of Andhra Pradesh.
# 35. In view of the foregoing discussion, we are of the considered opinion that the invocation of the Performance Bank Guarantee does not violate Section 14 of the IBC and the retention amount and deductions from RA bills are governed by contractual terms and cannot be directed to be refunded in the present proceedings. Further the disputes raised are predominantly contractual in nature and do not warrant interference under Section 60(5) of the Code. The Application is devoid of merit and is liable to be dismissed.
# 36. Accordingly, IA 109/2023 is dismissed. No order as to costs.
------------------------------------------