Tuesday, 24 November 2026

GS Megha Constructions Pvt. Ltd. vs Omkara Assets Reconstruction Pvt. Ltd. and Anr. - It is held that, there is no default as on date which led to commencement of the CIRP and therefore this company appeal deserves to be closed, while quashing the impugned order of 08.01.2026, in terms of the settlement, that has been arrived at between the parties, and owing to it, we are not required to venture into the merits of the matter.

  NCLAT (2026.11.20) in GS Megha Constructions Pvt. Ltd. vs  Omkara Assets Reconstruction Pvt. Ltd. and Anr. [(2026) ibclaw.in 1244 NCLAT, Company Appeal (AT) (CH) (Ins.) No. 46/2026 (IA Nos. 112, 113 & 114/2026)] held that; 

  • Thus, the sole controversy that would be emanating to be considered would be as to what would be the impact of acceptance of the onetime settlement and that too once the parties have proceeded to act upon the same by acceptance of the terms, and the Appellant has deposited the money of Rs. 5 Crores as a consequence on the Section 7 proceedings and whether thereafter the application under Section 7 could at all be directed to be admitted.

  • It is held that, there is no default as on date which led to commencement of the CIRP and therefore this company appeal deserves to be closed, while quashing the impugned order of 08.01.2026, in terms of the settlement, that has been arrived at between the parties, and owing to it, we are not required to venture into the merits of the matter.

Excerpts of the order;

The brief facts, which marginally require reference are that, by virtue of the impugned order of 08.01.2026, the corporate debtor, i.e., M/s GS Megha Constructions Pvt. Ltd., was directed to be admitted to the CIRP, by invocation of the provisions contained under Section 7 of the I&B Code.


# 2. As per the records, that were made available before the Ld. NCLT, the appellant was shown to have been sanctioned with term loan of Rs. 60 Crores by the DHFL, as far back as in the year 2015 for carrying out its construction and development activities. It is contended by the appellant, that there was a partial disbursal as against the total sanctioned loan amount, and the disbursement that was actually made was of a sum of Rs.33,50,00,000/- as would be apparent from the disbursement letter that was issued by the DHFL.


# 3. Subsequently, the said financial debt was assigned to Piramal Capital and Housing Finance Limited in 2021 who in turn assigned it to Omkara Asset Reconstruction Private Limited vide an assignment deed dated 10.01.2023. Omkara the Respondent No. 1 herein had invoked the proceedings under Section 7 of the IBC by filing the Section 7 application dated 31.07.2024, alleging a default of Rs. 1,29,73,95,652/- which was shown to be the defaulted amount standing as on 31.05.2024. After hearing both the parties and going through the records, Ld. NCLT allowed the Section 7 application and ordered commencement of CIRP against the Corporate Debtor, vide the impugned order dated 08.01.2026.


# 4. In Section 7 proceedings, before the proceedings could attain the stage of final hearing and after orders were reserved on the Section 7 petition, the Appellant initiated negotiation for entering into an amicable settlement so as to resolve the issue by offering a proposal of one-time settlement, which was formally accepted by the respondent, and a letter of intent was issued too on 18.12.2025 agreeing to settle the entire alleged dues for the consolidated sum of Rs. 50 Crores, taking it as to be the full and final settlement.


# 5. In compliance with the terms of settlement, the appellant is said to have deposited an upfront amount of Rs. 5 Crores by way of a demand draft dated 16.12.2025, which was received and acknowledged too by the respondent, which, according to the appellant, is an expression of his bonafide intention to settle the dispute inter se between the parties.


#3 6. It is argued by the learned counsel for the appellant by putting a challenge to the impugned order, that despite the fact that the binding settlement was still subsisting and is valid upto 07.09.2026 and the partial payment under the settlement that was made by the appellant has been received by the Financial Creditor, the Ld. NCLT has proceeded to pass the impugned order of 08.01.2026, thereby directing the admission of the Section 7 application, resulting into initiation of the CIRP.


# 7. The argument of the Ld. Counsel for the appellant has been that in light of the principles laid down in the judgment of Hon’ble Supreme Court passed in ‘Vidarbha Industries Power Ltd. v. Axis Bank Ltd.’ as reported in [(2022) ibclaw.in 91 SC] : [(2022) 8 SCC 352]. It has been laid down that the Tribunal has to exercise its discretion and to consider other relevant factors even when debt and default exist. But Ld. Tribunal did not exercise its discretion to defer the admission of CIRP even when a valid binding one-time settlement has been accepted between the parties. Thus, the sole controversy that would be emanating to be considered would be as to what would be the impact of acceptance of the onetime settlement and that too once the parties have proceeded to act upon the same by acceptance of the terms, and the Appellant has deposited the money of Rs. 5 Crores as a consequence on the Section 7 proceedings and whether thereafter the application under Section 7 could at all be directed to be admitted.


# 8. At this stage, we are not venturing upon the merits of the matter and we are not embarking to record our finding upon the ratio laid down by the judgment of Vidarbha Industries Power Ltd. v. Axis Bank Ltd. [(2022) ibclaw.in 91 SC], for the reason being that the said judgment has later on been reconsidered by the Hon’ble Apex Court, and it has been held, that it is not a judgment in rem, and that it was under that exceptional circumstances of that case, where the said ratio was propounded.


# 9. During the proceedings of the company appeal as against the impugned order, an interim order was passed on 27.01.2026, keeping the effect and operation of the impugned order on abeyance. Further, when the matter came for consideration on 21.09.2026, this Tribunal, recorded the statement made by the counsel for the appellant on record, that the appellant has already paid a partial payment, but owing to the fact that certain documents, which the purchaser had been seeking, have not been made available, the balance amount couldn’t be paid and that the said process is already under way, to complete the payment of entire amount as per the settlement agreement.


# 10. Further, on 08.10.2026, the learned counsel for the appellant made a statement that she has fully complied with the terms of the settlement and intends to place a memo to that effect. Accordingly, she has filed the memorandum on 08.10.2026 that stating that based upon the Letter of Intent dated 18.12.2025, issued by the Respondent which was in the shape of acceptance of the proposal of one-time settlement of dues, the Appellant has paid the entire amount of Rs. 50 Crore by 07.10.2026 which has been duly endorsed by the borrower as well as the Respondent Financial Creditor and which has been placed on record too. In that eventuality, as the parties are on a consensus based upon the terms referred to in the memorandum of settlement placed on record before us on 07.10.2026, we feel that no fruitful purpose would be served to venture into the appeal on its merit particularly when the parties have settled the dispute and no controversy pertaining to the remittance of the defaulted amount is left pending to be considered by us on merits. Hence, the company appeal would stand decided in terms of the settlement as produced by the learned counsel for the appellant.


#3 11. The company appeal is listed today for orders. A joint statement has been made by the learned counsel for the parties, that after passing of the orders by this Tribunal on 21.09.2026 to complete the payment, the full payment under the settlement agreement/letter of intent, has already been settled between the parties, and owing to the settlement that has been arrived at between the parties, in case the CIRP, which was directed to be initiated by virtue of the impugned order of 08.01.2026 is dropped, they may not have any grievances as such.


# 12. Considering the candid statement made by the learned counsel for the parties, and more particularly, the respondent as regards the fact that in pursuance to the settlement, that could be reflected in the pleadings before this Tribunal, that they have already received the full amount as settled between the parties, it is held that, there is no default as on date which led to commencement of the CIRP and therefore this company appeal deserves to be closed, while quashing the impugned order of 08.01.2026, in terms of the settlement, that has been arrived at between the parties, and owing to it, we are not required to venture into the merits of the matter. Hence, the company appeal would stand closed in terms of the onetime settlement that has been entered into between the parties on 18.12.2025. All interlocutory applications would stand disposed of.

----------------------------------------


Amier Hamsa Ali Abbas Rawther vs Principal Commissioner of Customs and Ors. - The object of the IBC is not allowed such guarantors to escape from an independent and co-extensive liability to pay off the entire outstanding debt, which is why section 14 of the IBC is not applied to them. Also held that contract of guarantee is between the creditor and principal debtor and the surety where under the creditor has a remedy in relation to his debt against both the principal debtor and surety.”

  NCLT Chennai (2026.11.05) in Amier Hamsa Ali Abbas Rawther vs  Principal Commissioner of Customs and Ors. [IA/267/(CHE)/2025 in CP/25(IB)/2022] held that; 

  • The object of the IBC is not allowed such guarantors to escape from an independent and co-extensive liability to pay off the entire outstanding debt, which is why section 14 of the IBC is not applied to them. Also held that contract of guarantee is between the creditor and principal debtor and the surety where under the creditor has a remedy in relation to his debt against both the principal debtor and surety.”

  • Once the BG is invoked by the beneficiary, the Margin Money lying with the bank goes towards payment of BG to the beneficiary leaving no scope for reversal of the Margin Money to the borrower as it is no longer part of the corpus of the Corporate Debtor.

Excerpts of the order;

# 1. Under consideration is an application filed by Liquidator of LSML Private Limited Company in Liquidation/ Corporate Debtor under Section 60(5) of Insolvency and Bankruptcy Code, 2016 (hereinafter, IBC, 2016) seeking the following reliefs:

  • a. Respondents 1 & 2 to not to encash the expired Bank Guarantees and maintain the status quo regarding the non-encashment of these guarantees

  • b. Order of stay on Respondents to not deal with encashing of the BG, until the disposal of the present application.

  • c. Respondent 3 to release the margin money from the two expired Bank Guarantees to the credit of the Corporate Debtor’s Current Account; and

  • d. To Pass any other order/orders that this Tribunal may deem fit and proper


FINDINGS OF THIS TRIBUNAL

# 44. Heard the Ld. Counsels for the parties and perused the documents placed on record.

# 45. To recapitulate the facts of the case, Respondent No. 2, the Deputy Commissioner of Customs, had granted the Corporate Debtor exemption from payment of import duty in respect of certain goods under the Advance Authorisation Scheme, in terms of Notification No. 018/2015 dated 01.04.2015. Pursuant thereto, the Corporate Debtor obtained Advance Licence No. 0410165252 dated 26.02.2019 and Advance Licence No. 0410166096 dated 20.09.2019. Under the terms of the said authorisations, the Corporate Debtor was required to fulfil its export obligations by 26.08.2020 and 20.03.2021, respectively, by utilising the imported materials for the purposes stipulated under the Scheme. To fulfil the condition for availing the benefit of the Scheme, Respondent No. 3, Punjab National Bank, issued Bank Guarantee No. 03051LG001319 dated 04.03.2019 for a sum of Rs. 6,25,600/- and Bank Guarantee No. 03051LG004319 dated 20.09.2019 for a sum of Rs. 27,50,850/-, in favour of the Customs Department. Respondent No. 3 issued extension letters dated 06.09.2022 and 29.10.2022 in respect of the subject Bank Guarantees dated 04.03.2019 and 20.09.2019 respectively. The Bank Guarantees were issued based on 100% Margin Money kept by way of the fixed deposit with PNB. The Corporate Debtor, however, failed to fulfil the export obligations and did not produce the requisite Export Obligation Discharge Certificate/Redemption Letter within the stipulated time.


# 46. The Corporate Insolvency Resolution Process against the Corporate Debtor commenced on 14.10.2022 pursuant to the order of this Tribunal passed in CP/IB/25/2022. Subsequently, an order of liquidation was passed on 02.10.2023 in IA(IBC)/1518/CHE/2023, and the Applicant was appointed as the Liquidator of the Corporate Debtor on 30.11.2023.


# 47. In view of the failure of the Corporate Debtor to fulfil its export obligations, the Customs Department, vide its letter dated 26.11.2024, called upon Respondent No. 3 to encash the subject Bank Guarantees. The Applicant, vide letter dated 29.11.2024, disputed the invocation on the ground that the Bank Guarantees had expired and sought the return of the fixed deposit amounts and margin money maintained with Respondent No. 3 in connection with the said guarantees.


# 48. The present Interlocutory Application has been filed by the Applicant/Liquidator seeking, inter alia, to restrain Respondent Nos. 1 and 2 from encashing the subject Bank Guarantees and to direct Respondent No. 3 to release the margin money/fixed deposit amounts furnished in connection with the Bank Guarantees to the liquidation estate of the Corporate Debtor. The Applicant’s case is founded primarily on the contention that the Bank Guarantees expired and cannot be enforced/invoked after expiry of the claim period and, consequently, the margin money ought to be returned to the Corporate Debtor.


# 49. Hence, the issue that arises for consideration is Whether the subject Bank Guarantees had expired or continued to subsist by virtue of the autorenewal clauses contained in the original guarantees, notwithstanding the validity and claim periods specified in the subsequent extension letters?


# 50. It is the case of the Applicant that the Bank Guarantees had expired, and that the Customs Department could not have invoked them beyond the validity and claim periods specified in the subsequent extension letters. On the other hand, the case of the Respondents is that the original Bank Guarantees contained an express stipulation requiring their automatic renewal until further directions were issued by the Customs Department or until the guarantees were expressly cancelled by the competent authority. This dispute requires an examination of the original contractual terms and the effect of the subsequent extension letters.


# 51. The original Bank Guarantee No. 03051LG001319 dated 04.03.2019, issued by Respondent No. 3 for a sum of Rs. 6,25,600/- in favour of the Deputy Commissioner of Customs, provided an unconditional guarantee by the issuing bank to secure the Customs Department against losses arising from the failure of the Corporate Debtor to comply with its export obligations. The second Bank Guarantee, issued in connection with Advance Licence No. 0410166096 dated 20.09.2019, provided for the payment of a sum of Rs. 27,50,858/-. Both Bank Guarantees were unconditional and irrevocable in nature, and the guaranteed amounts were payable without demur upon demand by the Customs Department. The relevant portion of the Bank Guarantee dated 04.03.2019 reads as follows:

  • Guarantee dated 04.03.2019

  • “7. Whereas, one of the conditions of the said notification being furnishing of surety or security by the importer for such sum as may be prescribed by the Deputy Commissioner of Customs, binding himself to pay on demand an amount equal to the duty leviable on the imported Material but for the exemption.

  • We, Punjab National Bank at the request of importer/Exporter to hereby unconditionally and irrevocably undertake to pay the government an amount not exceeding Rs. Six Lakh Twenty-Five Thousand Six Hundred Only, against any ‘loss, damage caused to or suffered by the government by reason of failure on the importer of any of the terms or conditions contained in the said Authorization and Notification No 018/2015 dated 01.04.2015 including export obligation mentioned therein.”


Bank Guarantee dated 20.09.2019:

# 52. A perusal of the original Bank Guarantees indicates that they contained a non-obstante auto-renewal clause, whereby Respondent No. 3 undertook to renew the Bank Guarantees from time to time until explicit directions were issued by the Customs Department for their cancellation. Thus, the auto-renewal obligation formed part of the contractual terms upon which the guarantees were furnished in favour of the Customs Department. The relevant auto-renewal clauses are extracted hereunder:

Bank Guarantee dated 04.03.2019:

Bank Guarantee dated 20.09.2019:

# 53. Respondent No. 3 subsequently issued extension letters dated 06.09.2022 and 29.10.2022 in respect of the Bank Guarantees dated 04.03.2019 and 20.09.2019, respectively. The particulars of the extension letters is as under:,


# 54. We refer to the extension letters dated 06.09.2022 and 29.10.2022 wherein there is another non obstante clause restricting the validity period up and the claim period for a period of 12 months thereafter. As per the renewal letter, the claim of the Customs Departments will be fulfilled if and only if the bank guarantee is invoked within the extended period. The non obstante clauses of the letters dated 06.09.2022 and 29.10.2022 are extracted hereunder,


# 55. This gives rise to an apparent conflict between the clauses contained in the original Bank Guarantees and those contained in the extension letters. Since both sets of clauses contain non-obstante wording, it is necessary to ascertain the intention of the parties by reading the original guarantees and the extension letters together, having regard to the purpose for which the guarantees were furnished.


# 56. At the outset, we consider the contention of the Applicant that, by virtue of the subsequent extension letters and the newly introduced non-obstante clauses, the terms of the original Bank Guarantees stood novated under Section 62 of the Indian Contract Act, 1872. In this regard, reference is made to Section 62 of the Act, which reads as follows:

  • 62. Effect of novation, rescission, and alteration of contract. —

  • If the parties to a contract agree to substitute a new contract for it, or to rescind or alter it, the original contract need not be performed.


# 57. The application of Section 62 of the Indian Contract Act, 1872, requires an examination ‘whether the parties to the original contract agreed to substitute a new contract for the existing contract, rescind the existing contract or alter its terms.’ In the present case, the clause relied upon by the Applicant to contend that the Bank Guarantees were altered to limit the claim period forms part of the extension letters issued by Respondent No. 3. However, the extension letters dated 06.09.2022 and 29.10.2022 were issued by Respondent No. 3 at the request of the Corporate Debtor. The letters were not issued pursuant to a fresh arrangement independently negotiated between the Customs Department and Respondent No. 3. No material has been placed on record to establish that the beneficiary, namely, the Customs Department, intended to alter or substitute the original contractual arrangement so as to dispense with the auto-renewal obligation. In the absence of such material, the reliance placed by the Applicant on the provisions relating to novation of contracts to extinguish the bank’s liability to renew the guarantees cannot be accepted. We, therefore, find that the original Bank Guarantees have not been shown to have been novated so as to extinguish the auto-renewal obligation.


# 58. The subsequent letters must, therefore, be understood as part of the same contractual arrangement. However, the inconsistency between the non-obstante clauses continues to subsist. Since the subsequent clause cannot be construed as having an overriding effect to corresponding clause in the original bank guarantee, the ambiguity, must be resolved by reading the contractual documents as a whole and ascertaining the intention manifested therein.


# 59. In this regard, it is seen that the extension letters expressly preserve the terms and conditions of the original Bank Guarantees. The said letters provide that the terms and conditions of the original Bank Guarantees shall remain unaltered and binding.


# 60. This stipulation indicates that the extension letters were issued to extend the guarantees while retaining the remaining contractual obligations including the auto renewal clause.


# 61. It is pertinent to note that the Reserve Bank of India Master Circular DBR. No. Dir. BC.11/13.03.00/2015-16 dated 01.07.2015, dealing with the conduct of guarantee business by banks, specifically recognises the requirement of an automatic extension clause in bank guarantees furnished in favour of Customs Houses. Clause 2.2.7.2(v) of the said Circular provides as follows:

  • “The Public Notice issued by the Customs Department stipulates, inter alia, that all bank guarantees furnished by an importer should contain a self-renewal clause inbuilt in the guarantee itself. As the stipulation in the Public Notice issued by the Customs Department is akin to the notice in the tender form floated by the DGS&D, the provision for automatic extension of the guarantee period in the bank guarantees issued to DGS&D, as at subparagraph (iv) above, should also be made applicable to bank guarantees issued favouring the Customs Houses”


# 62. The aforesaid notification supports the interpretation that the auto-renewal clause in guarantees furnished to Customs Department is intended to ensure continuity of the security furnished to the Customs Department. The original guarantees in the present case were issued in the context of the duty exemption availed of by the Corporate Debtor and contained an express auto-renewal clause. The subsequent extensions must, therefore, be construed consistently with the contractual obligation undertaken by Respondent No. 3 and the purpose for which the guarantees were issued. Where the original guarantee expressly requires automatic renewal until the requisite directions are issued by the Customs Department, a subsequent extension cannot be construed as extinguishing that obligation. A contrary construction would permit the issuing bank to dilute, by its unilateral act, an obligation that it had expressly undertaken in favour of the beneficiary.


# 63. It is pertinent to note that that Respondent No. 3, in its reply, has acknowledged that the Bank Guarantees contained an auto-renewal clause and has referred to its continuation pursuant to the said stipulation. This admission is consistent with the terms of the original guarantees and savings clause contained in the extension letters.


# 64. The original Bank Guarantees were furnished to secure compliance with the export obligations imposed under the Advance Authorisation Scheme. The auto-renewal clause was intended to ensure that the security furnished in favour of the Customs Department would not lapse merely with the passage of time while the underlying obligations remained unfulfilled and the requisite directions for cancellation had not been issued.


# 65. In view of the submissions of Respondent No. 3, the Circular of RBI dated 01.07.2015 and the saving clause in the extension letters upholding the terms of the original bank guarantees, the auto-renewal undertaking of the Respondent No. 3 is to be given effect. Accordingly, we find that the auto-renewal clause would extend the validity of the bank guarantee automatically after its expiry envisaged in the extension letters dated extension letters dated 06.09.2022 and 29.10.2022.


# 66. Now the issue arises: Whether the invocation of bank guarantee was in violation of the Section 14/ Section 33(5) of the Code?


# 67. The Hon’ble NCLAT in Bharat Aluminium Co. Ltd. v. J. P. Engineers Pvt. Ltd., (2021) ibclaw.in 91 NCLAT has held that an irrevocable and unconditional bank guarantee can be invoked even after the commencement of the CIRP of the Corporate Debtor and mortarium under the Code cannot restrict the right of the creditor to invoke the guarantee. The relevant paragraph is extracted hereunder:

  • “32. Hon’ble Supreme Court in the case V Ramakrishnan (Supra) held that sub-section 3(b) of Section 14 amendment being clarificatory in nature and is retrospective. Section 14 of the IBC refers only to debts due by Corporate Debtors, who are limited liability companies, and it is clear that the vast majority of the cases, personal guarantees are given by Directors who are not in management of the companies. The object of the IBC is not allowed such guarantors to escape from an independent and co-extensive liability to pay off the entire outstanding debt, which is why section 14 of the IBC is not applied to them. Also held that contract of guarantee is between the creditor and principal debtor and the surety where under the creditor has a remedy in relation to his debt against both the principal debtor and surety.”


# 68. The Bank Guarantees in question were issued by Respondent No. 3 in favour of the Customs Department to secure the obligations of the Corporate Debtor under the Advance Authorisation Scheme. The contractual liability under the guarantees is that of the issuing bank, subject to the terms of the bank guarantee. The commencement of the Corporate Insolvency Resolution Process or the subsequent liquidation of the Corporate Debtor does not, by itself, establish that the Bank Guarantees stood discharged or that the beneficiary was precluded from invoking them in accordance with their terms.


# 69. The Corporate Debtor admittedly failed to fulfil its export obligations within the stipulated periods causing the Advance Authorisation licenses to expire. The Customs Department thereafter invoked the guarantees by its letter dated 26.11.2024. Having found that the original auto-renewal obligation continued to subsist, and that the Applicant has not established that the guarantees stood discharged or cancelled before invocation, the said objection cannot be sustained. In these circumstances, the Applicant has failed to demonstrate that the actions complained of constitute a violation of the moratorium.


# 70. In view of our findings that the guarantees continued to subsist and, that their invocation is valid, no ground is made out for restraining Respondent No. 1 and 2 from encashing Bank Guarantees issued by Respondent No. 3 dated 04.03.2019 and 20.09.2019


# 71. Having held that the Bank Guarantees continued to subsist and that their invocation cannot be restrained, we proceed to consider the Applicant’s prayer for the release of the margin money/fixed deposit amounts maintained with Respondent No. 3.


# 72. In this regard, reference is made to the decision of the Hon’ble NCLAT in Indian Overseas Bank v. Consortium of GSEC Ltd. and Rakesh Shah and Anr., (2025) ibclaw.in 640 NCLAT wherein it was held that where the Bank Guarantee expires without invocation, the margin money may become refundable to the borrower, whereas, where the guarantee is invoked by the beneficiary and the bank becomes liable to make payment under the guarantee, the margin money may be applied towards the discharge of that liability. The relevant paragraph is extracted hereunder:

  • “30. We have already noticed for the reasons stated above that Margin Money in the given factual matrix does not fall within the definition of ‘security interest’. No security interest is created as such by the Corporate Debtor on the Margin Money. The Margin Money in the form of term deposit was a condition precedent for sanction of BGs. Margin Money in this case is the contribution on the part of the borrower seeking Bank Guarantee and the said Margin Money remained with the Bank as long as the Bank Guarantee was alive but once the Bank Guarantee was invoked by the beneficiary, the Margin Money went towards payment of Bank Guarantee to the beneficiary. The Margin Money component was in effect not the asset of the Corporate Debtor anymore. This Margin Money could be utilized by the Appellant Bank against invoked BGs as a matter of right under the Facility Agreement executed with the DPIL. Even if the appropriation of the Margin Money was not carried out by the Appellant Bank concurrently with the invocation of BG, the terms of the Facility Agreement did not impair the right of the Bank to credit unto itself the Margin Money sum at a later point of time. Even if the deduction was not carried out contemporaneously, it did not amount to extinguishment of the Bank’s contractual rights to do so subsequently. Once the BG is invoked by the beneficiary, the Margin Money lying with the bank goes towards payment of BG to the beneficiary leaving no scope for reversal of the Margin Money to the borrower as it is no longer part of the corpus of the Corporate Debtor. Thus, the Margin Money not being part of the asset of the Corporate Debtor anymore, the provisions of Section 14 do not become applicable on the Margin Money.”


# 73. In the present case, the margin money was furnished as a condition for the issuance of the Bank Guarantees and remained with Respondent No. 3 as security for the obligations undertaken by it in favour of the Customs Department. The margin money was thus not maintained as an ordinary deposit freely available to the Corporate Debtor without restriction. It was earmarked as security in connection with the Bank Guarantees. The entitlement of the Corporate Debtor to receive the amount back was consequently subject to the subsistence and discharge of the obligations secured by the guarantees.


# 74. Since it has been upheld that the guarantees continued to subsist, and that the invocation cannot be invalidated, the margin money never formed part of the liquidation estate of the Corporate Debtor.


# 75. Accordingly, the Applicant has failed to establish an entitlement to the unconditional release of the margin money/fixed deposit amounts maintained with Respondent No. 3, and the prayer for their release to the liquidation estate of the Corporate Debtor is rejected.


# 76. Hence, IA(IBC)/267/(CHE)/2025 is dismissed.

----------------------------------------


Monday, 23 November 2026

Navneet Kumar Gupta Vs. Ansal Properties and Infrastructure Limited - In view of the foregoing considerations, we are of the view that the projects and assets situated in Uttar Pradesh and those situated in Rajasthan should be dealt with separately for the purposes of the resolution process. Accordingly, the resolution process in respect of the specified projects and assets situated in Uttar Pradesh shall be administered separately from the resolution process in respect of the specified assets situated in Rajasthan.

  NCLT ND-IV (2026.11.19) in Navneet Kumar Gupta Vs. Ansal Properties and Infrastructure Limited [I.A 131 ND 2026 IN C.P. IB 558 (ND) 2024] held that;

  • Constituting a separate CIRP and CoC for each project at this stage may lead to multiplicity of processes and practical difficulties in dealing with common assets, liabilities, infrastructure and inter-project transactions. The State-wise arrangement, while maintaining separate CoCs for the two geographical regions, would facilitate effective administration and accountability and would not preclude consideration of project-wise or group-wise resolution plans within each State, subject to the provisions of the Code and the applicable CIRP Regulations.

  •  In view of the foregoing considerations, we are of the view that the projects and assets situated in Uttar Pradesh and those situated in Rajasthan should be dealt with separately for the purposes of the resolution process.  Accordingly, the resolution process in respect of the specified projects and assets situated in Uttar Pradesh shall be administered separately from the resolution process in respect of the specified assets situated in Rajasthan.

Excerpts of the order;

# 1. The present Application has been filed by the Applicant under Rule 11 of the National Company Law Tribunal Rules, 2016 (“NCLT Rules, 2016”) seeking the following reliefs:

  • a. Allow the present Application;

  • b. Kindly take on record the Judgment / Order dated 07.01.2026 passed by the Hon'ble Appellate Tribunal in Company Appeal No. 502 of 2025 titled as "Pranav Ansal VS IL&FS Financial Services Limited and Company Appeal No. 500 of 2025 titled as "Gagan Tondon VS IL&FS Financial Services Limited":

  • c. Pass such other order(s) as may be deemed fit and proper in the facts and circumstances of the case.


# 2. The Financial Creditor, IL&FS Financial Services Limited, had filed an Application Company Petition bearing C.P. (IB) No. 558 of 2024 under Section 7 of the Insolvency and Bankruptcy Code, 2016 (hereinafter referred to as "Code") seeking initiation of CIRP against the Corporate Debtor, which was admitted by this Adjudicating Authority vide Order dated 25.02.2025 and Mr. Navneet Kumar Gupta i.e., Applicant herein was appointed as an Interim 

Resolution Professional of the Corporate Debtor and a moratorium under Section 14 of the Code came into force.


# 3. In the interim the suspended board of director qua the Corporate Debtor Mr. Pranav Bansal filed an appeal bearing Company Appeal No. 502 of 2025 titled as "Pranav Ansal VS IL&FS Financial Services Limited on 05.03.2025 and one Mr. Gagan Tandon on 20.03.2025 also filed an appeal bearing Company Appeal No. 500 of 2025 titled as "Gagan Tondon VS IL&FS Financial Services Limited ("Appeals") before the Hon'ble NCLAT assailing the order dated 25.02.2025 challenging the initiation of CIRP qua the Corporate Debtor.


# 4. Subsequently, the Hon'ble NCLAT vide order dated 25.04.2025 passed an interim order in favour of the Appellants and stayed the issuance of FORM-G qua the Corporate Debtor.


# 5. Thereafter, the Hon'ble NCLAT, vide its final judgment and order dated 07.01.2026, disposed of the aforesaid Appeals with specific directions, while upholding the admission of the Corporate Debtor into CIRP, subject to the directions contained therein. The said judgment/order dated 07.01.2026 has a direct bearing on the ongoing CIRP proceedings and is therefore being placed on record before this Adjudicating Authority for consideration.


# 6. The Hon’ble NCLAT vide order dated 07.01.2026 issued the following directions:

  • “100. In view of the foregoing facts, we dispose of both the Appeal(s) in following manner: 

  • (1) The order dated 25.02.2025 passed by National Company Law Tribunal, New Delhi Bench Court-IV admitting Section 7 application is upheld, subject to following directions:

  • (a) The CIRP against the CD is confined to CD's projects at Lucknow Mother City and Mother City Extension at Lucknow, Golf Plots at Lucknow and the assets of the CD in the State of Rajasthan and builtup properties at Ajmer, Jodhpur and Jaipur in the State of Rajasthan (as detailed in Schedule-B of Settlement Agreement dated 03.03.2022 at Sl. No.5, 6 & 7).

  • (b) The Adjudicating Authority to consider the mode and manner to proceed with project wise resolution of the CD as per initiation of CIRP against a real estate company to the extent as indicated above. 

  • (c) Further steps in the CIRP of the CD shall be taken as per directions of the Adjudicating Authority indicated above. The Adjudicating Authority shall also consider with respect to resolution of the CD's project at Lucknow, as to whether as per MoU and Development Agreements entered between the CD and Lucknow Development Authority, the Lucknow Development Authority is to be directed to complete the projects of the CD. 

  • (d) UP Awas Evam Vikas Parishad shall be entitled to pursue its application before the Adjudicating Authority for excluding the assets claimed by it, from the CIRP of the CD, which may be considered and decided in accordance with law.

  • (e) The date of commencement of the CIRP of the CD has to be treated as 25.02.2025 and further steps in the CIRP be taken as per the directions of the Adjudicating Authority to be made hereinafter.

  • (f) The Lucknow Development Authority be made party to the CIRP process and it be given opportunity to file its affidavit. 

  • (g) The Homebuyers and other Applicants, who have filed IAs in these Appeal(s) are at liberty to file Intervention Petitions before the Adjudicating Authority in C.P.(IB) 558(ND)/2024.


# 7. The Financial Creditor, IL&FS Financial Services Limited, which had filed C.P. (IB) No. 558/ND/2024, preferred Civil Appeal Nos. 807-808 of 2026, IL&FS Financial Services Ltd. v. Pranav Ansal & Ors., before the Hon'ble Supreme Court assailing the Judgment dated 07.01.2026 passed by the Hon'ble Appellate Tribunal. By Order dated 16.04.2026, the Hon'ble Supreme Court declined to interfere with the impugned Judgment and disposed of the Civil Appeals, while upholding the Order passed by Hon’ble NCLAT.


# 8. We have considered the submissions of the Resolution Professional pursuant to the order dated 08.10.2026 and have perused the judgment dated 07.01.2026 passed by the Hon’ble National Company Law Appellate Tribunal (NCLAT) in Company Appeal (AT) (Ins.) Nos. 500 and 502 of 2025, the subsequent clarification dated 25.05.2026 and the order dated 16.04.2026 passed by the Hon’ble Supreme Court.


# 9. We have perused the order dated 07.01.2026 by the Hon’ble NCLAT and the same is taken on record. As per the order of the Hon’ble NCLAT, this Adjudicating Authority is to pass an order regarding the mode and manner to proceed with the resolution of the Corporate Debtor as per initiation of CIRP against a real estate company. Therefore, by this order, we are passing order regarding the mode and manner of the CIRP.


# 10. The Hon’ble NCLAT, while upholding the admission of the Corporate Debtor into CIRP, confined the CIRP to the projects of the Corporate Debtor at Lucknow, including Mother City, Mother City Extension and Sushant Golf City, as well as the assets of the Corporate Debtor situated in Rajasthan, including the built-up properties at Ajmer, Jodhpur and Jaipur. The Hon’ble NCLAT has expressly left the mode and manner of resolution of these projects and assets to be determined by this Adjudicating Authority. It has further directed that the CIRP shall proceed with effect from the commencement date of 25.02.2025 and that the question of completion of the Lucknow projects by the Lucknow Development Authority (LDA), in terms of the relevant Memorandum of Understanding and Development Agreements, shall also be considered.


# 11. Vide order dated 08.10.2026 passed in I.A. 2711 ND 2026, the order dated 25.05.2026 passed by the Hon’ble NCLAT in IA/3559/ND/2026 in Company Appeal (AT) (Insolvency) No. 500 of 2025 was taken on record wherein it was clarified that in addition to the projects namely Mother City Lucknow and Mother City Extension Lucknow, the CIRP shall also extend to and remain confined to the Corporate Debtor's projects situated in Sushant Golf City as well as the assets of the Corporate Debtor in the State of Rajasthan.


# 12. The issue before us is, therefore, not whether the CIRP is to continue, as the admission order already stands upheld by the Hon’ble NCLAT and the Hon’ble Supreme Court has declined to interfere with the same. The question that arises for consideration is the mode and manner in which the CIRP is to be operationalised in respect of the projects and assets specifically identified by the Hon’ble NCLAT. The mechanism adopted must give effect to the aforesaid directions, facilitate value maximisation, protect the interests of the stakeholders and ensure that the CIRP progresses expeditiously in accordance with the provisions of the Code.


# 13. During the course of the proceedings, certain homebuyers filed I.A. 5159/ND/2026 seeking, inter alia, separate CIRPs and separate Committees of Creditors (CoCs) for each project of the Corporate Debtor. Vide order dated 28.10.2026, this Adjudicating Authority recorded the submission of the learned Counsel appearing on behalf of the applicants. The applicants contended that a project-wise CIRP and separate CoCs for each project were necessary to safeguard the interests of homebuyers associated with different projects. Having considered the said submission, this Adjudicating Authority observed that the issue regarding the mode and manner of the CIRP raised by the Applicant, including the request for separate project-wise CIRPs and CoCs, would be considered while deciding the present Application.


# 14. The Hon’ble NCLAT, vide its judgment dated 07.01.2026, confined the CIRP to the specified projects of the Corporate Debtor situated in the State of Uttar Pradesh, namely, Mother City, Mother City Extension and the projects situated in Sushant Golf City, Lucknow, together with the assets of the Corporate Debtor situated in the State of Rajasthan, including the built-up properties at Ajmer, Jodhpur and Jaipur. Thus, the assets falling within the scope of the CIRP are situated in two distinct geographical regions, namely, Uttar Pradesh and Rajasthan. The nature and location of these assets, the separate project requirements and the need for effective coordination with the respective local authorities warrant consideration while determining the appropriate mechanism for resolution.


# 15. We are of the considered view that administering all the aforesaid projects and assets through a single CIRP and a common Resolution Professional may give rise to practical difficulties in the identification and segregation of projectspecific assets and liabilities, determination of the claims attributable to each geographical region, management of project-specific funds and formulation and implementation of viable resolution proposals. Further, a common Committee of Creditors (CoC), comprising stakeholders whose interests may be confined to different projects and geographical regions, may complicate the determination of voting shares and the assessment of resolution proposals in relation to the respective projects and assets. These considerations assume particular significance in the present case, wherein the scope of the CIRP has expressly been restricted by the Hon’ble NCLAT to specified projects and assets, rather than the entire Corporate Debtor as a whole.


# 16. The geographical separation of the assets between Uttar Pradesh and Rajasthan, coupled with the need for independent project-wise assessment, effective supervision and accountability, constitutes a relevant consideration in determining the mode and manner of resolution. A separate Resolution Professional for each region would facilitate the identification and management of the assets situated therein, verification of the claims and liabilities attributable to the respective projects, maintenance of appropriate financial records and coordination with the concerned authorities and stakeholders. It would also facilitate the formulation and consideration of resolution proposals suited to the particular circumstances of the projects and assets falling within each region. We have also considered the concerns raised by the homebuyers in I.A 5159 of 2026. Constituting a separate CIRP and CoC for each project at this stage may lead to multiplicity of processes and practical difficulties in dealing with common assets, liabilities, infrastructure and inter-project transactions. The State-wise arrangement, while maintaining separate CoCs for the two geographical regions, would facilitate effective administration and accountability and would not preclude consideration of project-wise or group-wise resolution plans within each State, subject to the provisions of the Code and the applicable CIRP Regulations.


# 17. In view of the foregoing considerations, we are of the view that the projects and assets situated in Uttar Pradesh and those situated in Rajasthan should be dealt with separately for the purposes of the resolution process.  Accordingly, the resolution process in respect of the specified projects and assets situated in Uttar Pradesh shall be administered separately from the resolution process in respect of the specified assets situated in Rajasthan. For this purpose, a separate Resolution Professional shall be appointed for each of the two processes. We hereby appoint the following Resolution Professionals:


A. Rajasthan: For projects in Rajasthan, we retain the present Resolution Professional to discharge functions in accordance with the Code and Regulations thereunder. The details of the Resolution Professional are as follows:

Name: Mr. Navneet Kumar Gupta

Registration No. : IBBI/IPA-001/IP-P00001/2016-2017/10009

E-mail : navneet[at]minervaresolutions[dot]com


B. Uttar Pradesh: For projects situated in Uttar Pradesh, we hereby appoint Mr. Surendra Raj Gang as the Resolution Professional to discharge function in accordance with the Code and Regulation thereunder. The details of the Resolution Professional are as follows:

Name: Mr. Surendra Raj Gang

Registration No. : IBBI/IPA-001/IP-P01066/2017-2018/11773

E-mail : surendra[dot]Raj[at]in[dot]gt[dot]com


The RP so appointed shall file consent in Form-2, a valid AFA and  disclosure about non-initiation of any disciplinary proceedings against him, within three working days (3) of pronouncement of this order. 


# 18. Each Resolution Professional shall be responsible for the identification, verification and management of the assets and liabilities falling within the respective geographical scope, as well as for undertaking the steps necessary for resolution in accordance with law.


# 19. The first resolution process shall be confined to the Corporate Debtor’s projects situated in Uttar Pradesh, namely, Mother City, Mother City Extension including projects situated in Sushant Golf City, Lucknow, together with the assets and liabilities attributable to those projects. The second resolution process shall be confined to the assets of the Corporate Debtor situated in Rajasthan, including the built-up properties at Ajmer, Jodhpur and Jaipur, as specified at Serial Nos. 5, 6 and 7 of Schedule-B to the Settlement Agreement dated 03.03.2022. Neither process shall extend to any other project, asset or undertaking of the Corporate Debtor beyond the scope identified by the Hon’ble NCLAT.


# 20. For implementing the aforesaid arrangement, the existing Resolution Professional shall cooperate in the transition and hand over the relevant records, claims, financial information and project-specific particulars of the Projects in Uttar Pradesh to the Resolution Professional appointed for Uttar Pradesh within 4 weeks from the date of pronouncement of this order.


# 21. In addition to the aforesaid arrangement, we deem it appropriate to appoint one common Supervisor for both the resolution processes to ensure effective coordination, monitoring and uniformity in the administration of the two processes. The Supervisor shall oversee the functioning of both Resolution Professionals, monitor the progress of the respective resolution processes and facilitate coordination between them, wherever required, without interfering with their independent statutory functions and responsibilities under the Code and the Regulations framed thereunder. 


# 22. The remuneration of the Ld. Supervisor shall be fixed at Rs. 2,00,000/- (Rupees Two Lakhs only) per month, along with reimbursement of other expenses incurred in the discharge of his duties on an actual basis. The aforesaid remuneration and expenses shall be borne and paid by the Committee of Creditors (CoC) constituted in respect of the Uttar Pradesh projects. Both Resolution Professionals shall extend full cooperation and provide such information and assistance as may be required by the Ld. Supervisor. The Ld. Supervisor shall file a consolidated progress report before this Adjudicating Authority every 90 days. We hereby appoint the following to supervise the 2 Resolution Processes:


Name: Mr. Mukul Singhal

E-mail: mukulsinghal2@gmail.com

Contact No. : 8765179988

The Ld. Supervisor shall file his consent within 3 working days from the date of pronouncement of this order.


# 23. The Resolution Professionals shall prepare and file before this Adjudicating Authority a comprehensive project-wise assessment of the assets, liabilities and financial affairs attributable to the projects and assets falling within the scope of the CIRP in which they are appointed. The assessment shall include details of movable and immovable assets, project-wise liabilities and admitted claims, receivables, loans and borrowings, securities and encumbrances, bank accounts and balances, funds received and utilised, and any interproject transfers or common expenses. Wherever any asset, liability, fund, receivable or expenditure pertains to more than one project or cannot be directly attributed to a particular project, the Resolution Professional shall identify the same and provide a reasoned pro rata allocation, specifying the basis and methodology adopted.


# 24. The Resolution Professionals shall also identify common infrastructure, shared resources and cross-collateralisation of assets, wherever applicable, and clearly distinguish project-specific assets and liabilities from those which are common to multiple projects. The assessment shall be supported by relevant records and documents and shall provide a clear account of the assets and liabilities attributable to the respective geographical regions. The aforesaid assessment shall be filed by way of an affidavit within 4 weeks from the transition and handover as mentioned in Para 20 of this order. The Resolution Professionals shall not, merely by reason of the proposed geographical segregation, transfer, appropriate or exclude any asset or liability without due verification and compliance with the applicable provisions of law.


# 25. In order to have clarity, it is stated that there would be 2 CoCs i.e. one for the UP Projects and one for the Rajasthan Projects. The existence of different CoCs (one for UP and one for Rajasthan) does not preclude consideration of separate resolution plans for individual projects or groups of projects within each state. The Resolution Professionals appointed for the respective resolution processes are directed to verify and collate the claims of the creditors pertaining to the projects and assets falling within their respective jurisdictions and constitute  the CoCs for the respective processes in accordance with the provisions of the Code and the applicable CIRP Regulations. The respective Resolution Professionals shall conduct the CIRPs in accordance with the provisions of the Code and the applicable CIRP Regulations. The RP and the CoC of both processes may consider a composite plan or project-wise/group-wise plans in accordance with the Code and the applicable CIRP Regulations, including Regulation 36A.


# 26. In the event any Resolution Professional identifies any asset, liability, receivable, bank account or transaction that appears to have been incorrectly included within or excluded from the scope of the respective CIRPs, the RP shall place the relevant particulars before this Adjudicating Authority and seek appropriate directions before taking any consequential action.


# 27. The question concerning the take-over of the Lucknow projects by the Lucknow Development Authority (LDA) form subject matter of in I.A. 4747/2026 filed by LDA and therefore shall be considered separately in I.A. 747/2026, after affording an opportunity of hearing to the LDA, the RP and  other concerned parties. No final opinion is expressed on the merits of the issue at this stage.


# 28. The RPs shall proceed with the CIRP expeditiously and in accordance with the directions of the Hon’ble Supreme Court and the Hon’ble NCLAT, as well as the applicable provisions of the Code and the CIRP Regulations. 


# 29. The application filed by the Uttar Pradesh Awas Evam Vikas Parishad (UPAVP), if any, seeking exclusion of the assets claimed by it from the scope  of the CIRP shall be considered separately in accordance with the directions of the Hon’ble NCLAT and provisions of law.


# 30. A copy of the order shall be communicated to the Resolution Professionals and the Ld. Supervisor above named, by the Registry.


# 31. In addition, a copy of the order shall also be forwarded to IBBI for its records. 

# 32. The present Application bearing I.A. 131 ND 2026 is disposed of in the above Terms.

------------------------------------------------


Disclaimer:

The sole purpose of this post is to create awareness on the "IBC - Case Law" and to provide synopsis of the concerned case law, must not be used as a guide for taking or recommending any action or decision. A reader must refer to the full citation of the order & do one's own research and seek professional advice if he intends to take any action or decision in the matters covered in this post.