Sunday, 1 June 2025

Manjeet Bucha IRP of Trident Sugars Ltd. - In the light of the above circumstances, as the claims were filed within 7 days period in pursuance of regulation 13(1)(1C) and the Committee of creditors has taken a note on the same in its 13th Committee of creditors meeting, we condone the delay as prayed by the Resolution Professional.

  NCLY Hyd. (2025.04.28) in Manjeet Bucha IRP of Trident Sugars Ltd. [(2025) ibclaw.in 529 NCLT, I.A. (IBC) No. 320 of 2025 in C.P. (IB) No. 259/7/HDB/2023] held that.-  

In the light of the above circumstances, as the claims were filed within 7 days period in pursuance of regulation 13(1)(1C) and the Committee of creditors has taken a note on the same in its 13th Committee of creditors meeting, we condone the delay as prayed by the Resolution Professional.

  • However, the second relief sought for exclusion of the period of pendency of this application with the Tribunal is rejected as time taken in adjudication of any application can not be excluded from the time taken in Corporate Insolvency Resolution Process. But, we grant leave to resolution professional to file an application for extension of Corporate Insolvency Resolution Process if required.


Excerpts of the Order;

# 1. This Application is filed by the Applicant/Resolution Professional under Section 25(e) and 60(5) of the Insolvency and Bankruptcy Code, 2016 read with Regulation 13 of the Insolvency and Bankruptcy Board of India (Insolvency Resolution Process for Corporate Persons Regulations) 2016, inter alia, seeking the following relief:

  • 1. “To condone the claims received under the regulation 13(1B) of IBBI (CIRP) Regulations, 2016 which is enclosed as Annexure-3” and

  • 2. “To exclude the period during which the present application is pending before this Hon'ble Tribunal from its date of filing till the date of disposal”.


1. The averments of the Applicant in brief are as follows:

1.1. It is averred that following a Company Petition filed by the Financial Creditor/M/s. Prudential Ammana Sugars Limited under Section 7 of the Insolvency and Bankruptcy Code, 2016 (“IBC”), Corporate Insolvency Resolution Process (“CIRP’) of M/s.Trident Sugars Limited/Corporate Debtor was commenced on 09.07.2024 by order of this Tribunal in  CP(IB).No.259/7/HDB/2023. Subsequently, the Applicant was appointed as the Interim Resolution Professional (“IRP”) and later confirmed as the Resolution Professional (“RP”) at the first Committee of Creditors meeting held on 06.08.2024.


# 2. It is averred that a Public Announcement of CIRP (Form-A) dated 12.07.2024 was issued under Regulation 6 of Insolvency and Bankruptcy Board of India (Insolvency Resolution Process for Corporate Persons) Regulation 2016, which was published in Financial Express (English) and Nava Telangana (Telugu) on 13.07.2024 for inviting claims from creditors/stakeholders by 26.07.2024. Pursuant to the public announcement, claims were received from financial creditors, operational creditors and other creditors, and the Committee of Creditors was constituted by the Resolution professional. The same was recorded by this Tribunal vide order dated 03-10-2024 in IA(IBC) No. 1937/2024.


# 3. It is averred that following the constitution of the Committee, the Resolution professional received a claim of Rs.33,00,000/- from the Financial Creditor/Mr. Harisainath Reddy on 06.08.2024. The Resolution professional after verification and admission of the said claim reconstituted the Committee of creditors. Subsequently, Form G was published on 27.08.2024 in Financial Express (English) and Nava Telangana (Telugu).


# 4. It is further averred that the Applicant requested for the Resolution Plan (RFRP) to the Prospective Resolution Applicants on 05.10.2024. Further, under the proviso to Regulation 12 of IBBI (Insolvency Resolution Process for Corporate Persons) Regulations, 2016, requested the creditors who failed to submit claims as per public announcement within deadline of 26.07.2024, to submit claims until the date of RFRP or with 90 days of commencement of CIRP i.e by 07.10.2024, whichever is later.


# 5. It is averred that the final list of Prospective Resolution Applicants was made, and the original deadline for submitting the resolution plan was 09.11.2024. However, the Committee of Creditors (CoC) extended this deadline to 12.12.2024. As a result of the extension, the RP received claims from creditors after the deadline period dated 07.10.2024. Therefore, the following claims were received as under: . . . . .


# 6. It is averred that under Regulation 13(1B), of IBBI (CIRP) Regulation, 2016, if claims are received after the deadline specified in Regulation 12(1) but before seven days of the creditors' meeting for voting on the resolution plan or liquidation, the Resolution Professional shall verify and categorize them as acceptable or non-acceptable for collation. As per Regulation 13(1C), the Resolution Professional must notify the creditor of the categorization within seven days and provide reasons for non-acceptance. Further, acceptable claims are to be presented to the Committee of Creditors for inclusion in the list of creditors and treatment in the resolution plan. The Resolution Professional must also submit these claims to the Adjudicating Authority for condonation of delay and adjudication where necessary. Therefore, the Applicant filed the present application for condonation of the delay in receiving claims under Regulation 13(1B).


# 7. In the light of the contest as afore stated, the point that emerges for our consideration is:

  • Whether the Adjudicating Authority can condone the delay for claims received by the Applicant/Resolution Professional under Regulation 13(1B) of Insolvency and Bankruptcy Broad of India (Insolvency Resolution Process for Corporate Persons) Regulations, 2016?


# 8. We have heard the Learned Resolution professional, Mr. Manjeet Bucha and perused the records.


# 9. At the outset we find it useful to refer the relevant Regulation of CIRP process i.e., Regulations 12 and 13 of Insolvency and Bankruptcy Broad of India (Insolvency Resolution Process for Corporate Persons) Regulations, 2016 extracted as under:

  • “12. Submission of proof of claims:

  • (1) A creditor shall submit claim with proof on or before the last date mentioned in the public announcement: Provided that a creditor, who fails to submit claim with proof within the time stipulated in the public announcement, may submit his claim with proof to the interim resolution professional or the resolution professional, as the case may be, up to the date of issue of request for resolution plans under regulation 36B or ninety days from the insolvency commencement date, whichever is later: Provided further that the creditor shall provide reasons for delay in submitting the claim beyond the period of ninety days from the insolvency commencement.

  • (2)…………

  • (3) Where the creditor in sub-regulation (2) is a financial creditor under regulation 8, it shall be included in the committee from the date of admission of such claim: Provided that such inclusion shall not affect the validity of any decision taken by the committee prior to such inclusion.”

  • “13. Verification of claims:

  • (1) The interim resolution professional or the resolution professional, as the case may be, shall verify every claim, as on the insolvency commencement date, within seven days from the last date of the receipt of the claims, and thereupon maintain a list of creditors containing names of creditors along with the amount claimed by them, the amount of their claims admitted and the security interest, if any, in respect of such claims, and update it.

  • (1A) Where the interim resolution professional or the resolution professional, as the case may be, does not collate the claim after verification, he shall provide reasons for the same.

  • (IB) In the event that claims are received after the period specified under sub-regulation (1) of regulation 12 and up to seven days before the date of meeting of creditors for voting on the resolution plan or the initiation of liquidation, as the case may be, the interim resolution professional or resolution professional, as the case may be, shall verify all such claims and categorise them as acceptable or non-acceptable for collation.

  • (IC) The interim resolution professional or resolution professional, as the case may be, shall:

  • (a) intimate the creditor within seven days of categorisation thereof under sub-regulation (IB) and provide reasons where such claim has been categorised as non-acceptable for collation; and

  • (b) put up the claims categorised as acceptable under sub- regulation (IB) and collated by him to:-

  • (i) the committee in its next meeting for its recommendation for inclusion in the list of creditors and its treatment in the resolution plan, if any; and

  • (ii) submit such claims before the Adjudicating Authority for condonation of delay and adjudication wherever applicable.”


# 10. From the above regulations we observe that, Regulation 13 (1B) provides for receiving claims after the period specified in Regulation 12 (1) and only up to 7 days before the Date of meeting of Creditors for voting on the Resolution Plan or the initiation of Liquidation. The regulation further directs the Resolution Professional depending upon the case, to verify and

categorize such claims. The Regulation 13 (1C) also mandates the Resolution Professional firstly to intimate the Creditor within 7 days along with reasons from categorisation of claim as non-acceptable for collation and secondly to put the claims which are categorised as acceptable and collated before the CoC for recommendation for inclusion of the creditors in the list of Creditors and its treatment in the resolution plan. Additionally, the second condition also directs the Resolution Professional to submit the delayed claims as specified in Regulation 13 (1B) which are categorised as acceptable, collated and recommended by the CoC before the Adjudicating Authority for Condonation of delay and adjudication.


# 11. In the case on hand, public announcement notice (Form A) was issued on 12.07.2024 wherein the last date for receiving claims by the Interim Resolution Professional was set as 26.07.2024. However, the applicant stated that four claims were submitted after the stipulated deadline. Among those, the claim from the property tax creditor, amounting to Rs. 8,33,620/-was received by the Resolution Professional on 21.11.2024 and was accepted in accordance with Regulation 13(1)(1B). In contrast, the claims received from Mr. V. Vijay Kumar for Rs. 5,98,890/- on 27.11.2024, Mr. B. Malla Reddy for Rs. 1,74,350/- and M/s. Laxmi Manvitha Chemicals for Rs. 39,18,170/- on 17.12.2024, were rejected as time-barred in the 9th Committee meeting held on 28.11.2024. Subsequently, the Resolution professional has stated that the collated claims were placed before the committee of creditors.


# 12. Pursuant thereto on 21.03.2025, this Tribunal directed the applicant to submit the copy of minutes of meeting of the committee of creditors in which claims were placed before the committee of creditors and was approved. Pursuant to the directions of this Tribunal the applicant filed the 13th Minutes of Meeting of committee of creditors dated 21.12.2024 on 24.03.2025 and the same was taken on record.


# 13. On perusal of the 13th Minutes of Meeting of committee of creditors dated 21.12.2024, we found that as per the regulation 13(1)(1C) the resolution Professional has verified and collated the claims, accepting certain claim while rejecting others. Further, the Resolution Professional in compliance with the regulations, has reported the collated claims and placed the revised list of claims as on 18.12.2024 before the committee of creditors in the 13th meeting wherein the same was taken on note by the committee.


# 14. In the light of the above circumstances, as the claims were filed within 7 days period in pursuance of regulation 13(1)(1C) and the Committee of creditors has taken a note on the same in its 13th Committee of creditors meeting, we condone the delay as prayed by the Resolution Professional.


# 15. However, the second relief sought for exclusion of the period of pendency of this application with the Tribunal is rejected as time taken in adjudication of any application can not be excluded from the time taken in Corporate Insolvency Resolution Process. But, we grant leave to resolution professional to file an application for extension of Corporate Insolvency Resolution Process if required.


# 16. Accordingly, this application is partly allowed and disposed off. 


-------------------------------------------------


Monday, 10 March 2025

Riddhi Siddhi Gluco Biols Ltd. Vs. Sunit Jagdishchandra Shah (RP) - Clearly enough, CoC having taken a considered decision in this regard, this constituted sufficient grounds for the Adjudicating Authority to extend further time beyond 330 days for completion of the CIRP process.

 NCLAT (2025.03.07) in Riddhi Siddhi Gluco Biols Ltd. Vs. Sunit Jagdishchandra Shah (RP). [((2025) ibclaw.in 172 NCLAT, Company Appeal (AT) (Insolvency) No. 187 of 2025] held that;

  • In the present case, the 23rd CoC meeting on 04.12.2023 had taken note of the fact that it was in an advanced stage of considering the resolution plans before it and since the extended CIRP period was getting expired on 10.12.2023, the CoC approved seeking further extension of CIRP period.

  • Clearly enough, CoC having taken a considered decision in this regard, this constituted sufficient grounds for the Adjudicating Authority to extend further time beyond 330 days for completion of the CIRP process.

  • There can be no fetters on the commercial wisdom of CoC. The supremacy of commercial wisdom of CoC has been reaffirmed time and again by the Hon’ble Supreme Court in a catena of judgements

  • So long the statutory provisions of the IBC and the CIRP Regulations framed thereunder are complied with, it is the commercial wisdom of the requisite majority of the CoC which is to negotiate and accept a resolution plan.

  • Once all the mandatory requirements have been duly complied with and taken care of, judicial review cannot be extended to analyse and look into the dissatisfaction evinced by any particular creditor or stakeholder.

  • The Adjudicating Authority cannot substitute its views with the commercial wisdom of the CoC nor deal with the merits of Resolution Plan unless it is found it to be contrary to the express provisions of law and against the public interest.

  • In the present case when no valid grounds have been made out to challenge the approval of the resolution plan, the legislative fiat of the IBC that the Adjudicating Authority cannot trespass upon the business decision of the CoC holds ground.


Excerpts of the Order;

The present appeal filed under Section 61 of Insolvency and Bankruptcy Code 2016 (‘IBC’ in short) by the Appellant arises out of the Order dated 27.11.2024 (hereinafter referred to as ‘Impugned Order’) passed by the Adjudicating Authority (National Company Law Tribunal, Ahmedabad Bench-II) in IA No 6 of 2024 in CP(IB)/9(AHM)2021. By the impugned order, the Adjudicating Authority has approved the resolution plan of the Corporate Debtor as submitted by the Resolution Professional. Aggrieved by the impugned order, the present appeal has been preferred by the Appellant-Operational Creditor.


# 2. The sequence of events which are necessary to be noticed for deciding the present appeal are as follows:

  • On 07.12.2022, the CIRP of the Corporate Debtor was initiated and IRP was appointed.

  • The IRP constituted the CoC comprising of two Secured Financial Creditors and two Unsecured Financial Creditors. The first CoC meeting was held on 13.01.2023.

  • On 10.03.2023, the Form-G was published by the IRP inviting EOIs.

  • On 05.06.2023, the CIRP period of 180 days had expired. The Resolution Professional (“RP” in short) filed an application before the Adjudicating Authority for extension of CIRP period for 90 days which was allowed on 19.06.2023.

  • In the 14th CoC meeting held on 29.08.2023, the CoC resolved to extend the CIRP period beyond 270 days. This was allowed by the Adjudicating Authority on 06.10.2023.

  • On 19.10.2023, the 17th CoC meeting directed the RP to file application for extension of CIRP period as it wanted to discuss the resolution plan submitted by Mercury Terra Firma.

  • On 30.12.2023, the Adjudicating Authority allowed extension of CIRP period upto 10.12.2023, while also directing the RP to expedite the CIRP process.

  • The 19th CoC meeting held on 01.11.2023 decided to reissue Form-G. Accordingly, the RP republished Form-G on 03.11.2023.

  • The CoC considered the EOIs received in the 21st and 22nd CoC meetings. Since the 23rd CoC meeting held on 04.12.2023 was still considering the resolution plans and needed further time for consideration and the CIRP period was expiring on 10.12.2023, the RP moved the Adjudicating Authority for seeking further extension of CIRP for a period of 60 days.

  • Extension of CIRP period upto 20.02.2024 was allowed on 08.01.2024 by the Adjudicating Authority.

  • On 29.01.2024 the CoC approved the resolution plan submitted by Mercury Terra Firma which was approved with 97.36% voting.

  • The Adjudicating Authority passed the impugned order on 27.11.2024 approving the resolution plan.

  • Aggrieved by the impugned order approving the resolution plan, the present appeal has been preferred by the Appellant- Operational Creditor.


# 3. Making his submissions, the Ld. Counsel for the Appellant submitted that the Adjudicating Authority approved the resolution plan in violation of Section 12 of the IBC by allowing repeated extensions of CIRP even beyond 330 days. Extension had been allowed beyond the period of 330 days without adequate justification. Highlighting other procedural and material irregularities, it was submitted that the RP had re-published the Form-G on 03.11.2023 only in the newspapers and not on the website of IBBI which amounted to non-compliance of Regulation 36-A(2) of the IBBI (Insolvency Resolution Process for Corporate Persons) Regulations, 2016 (“CIRP Regulations” in short). It is also contended that though the Appellant in the 17th CoC Meeting on 19.10.2023 had sought valuation reports, the RP did not circulate the valuation report of the Corporate Debtor either to the Appellant or to other members of the CoC but only furnished bare figures of fair value and liquidation value. In the absence of valid and detailed valuation reports, the CoC would have been handicapped to exercise its commercial wisdom judiciously. However, the Adjudicating Authority has overlooked these procedural irregularities in approving the resolution plan.


# 4. It was also pointed out that the RP had admitted claim of Rs 69,08,949/-claimed by the Appellant and that the aggregate admitted claim of all Operational Creditors put together worked out to Rs 18,34,60,969/-. However, as against a composite claim of Rs 18.34 Cr. of the Operational Creditors, the Successful Resolution Applicant has offered only Rs 60 lakhs for payment to Operational Creditors. The resolution plan therefore prejudiced the interests of Operational Creditors and amounted to non-compliance with Section 30(2)(b) of IBC.


# 5. Refuting the contentions raised by the Appellant, the Ld. Counsel for the Respondent submitted that the resolution plan could have been challenged only on the grounds laid down under Section 61(3) of the IBC but no such grounds have been substantiated by the Appellant in the present appeal. On the contention that the RP had only shared naked figures of fair value and liquidation value instead of providing the detailed valuation report, it was submitted that the 17th CoC meeting had after due deliberations recorded the reasons for not sharing the full valuation report with the Appellant. In any case, the Appellant being an Operational Creditor having no voting rights it was of no consequence whether the detailed valuation report was placed before them or not since it was the members of the CoC who were required to exercise their commercial wisdom on the valuation reports placed before them. Moreover, the Appellant had participated in the CoC meetings but not having raised any objections earlier on this count cannot do so now. It was also contended that the Adjudicating Authority was empowered to complete the resolution process by extending the 330 day time-line because the resolution plan was at advanced stage of consideration of the CoC and the CIRP timelines were getting over soon. It was contended that the Appellant has failed to explain how it was aggrieved by the resolution plan which had been approved by the Adjudicating Authority after allowing extended time-lines. The Appellant had been a regular participant in the CoC meetings but never opposed the extension of CIRP time-lines. Not having raised such objections earlier, the Respondent cannot raise this issue at this belated stage. It was also pointed out that the Respondent cannot complain about the treatment meted out to the Operational Creditors in the resolution plan since they had received more than the minimum entitlement in terms of liquidation value which was kept at Nil for Operational Creditors. It was also pointed out that when the resolution plan had been approved by the CoC with 97.36% voting, the Adjudicating Authority had no option to traverse beyond the commercial wisdom of the CoC. In any case, it was vehemently contended that the resolution plan already stands implemented and therefore cannot be reversed when the Appellant has failed to make out any ground as to how the resolution plan was non-compliant of Section 30(2) of IBC.


# 6. We have duly considered the arguments advanced by the Learned Counsel for both the parties and perused the records carefully.


# 7. The short point for our consideration is whether there were material irregularities in the exercise of powers by the RP in the CIRP proceedings; whether the claims of the Operational Creditors did not receive their dues or whether there was any contravention of the provisions of law.


# 8. Coming to the contentions raised by the Appellant with regard to material and procedural irregularities, we find that the Appellant has assailed the impugned order approving the resolution plan on the ground that the plan was approved by the Adjudicating Authority after expiry of 330 days of CIRP period. There is no doubt that in terms of Section 24(3)(c) of the IBC, it is the duty of the RP to give notice to the Operational Creditors or their representatives regarding the CoC meetings if the amount of their aggregate due is not less than 10% of the debt. It is also well settled that such Operational Creditors whose aggregate due is not less than 10% of the debt have a right to watch the proceedings of the CoC and express their views in the meetings without however any right to vote. In the present case, there is no denial of the fact that the Appellant received notice of the CoC meetings from the RP. As the Appellant was kept informed of the CoC meetings and records show their regular participation in such meetings, they had full knowledge of the CIRP proceedings. They were therefore equally aware of the extensions of CIRP time-lines approved by the CoC but these extensions by the CoC were not questioned by them at the appropriate time. The issue was neither agitated before the Adjudicating Authority at the right point of time and is now being raked up belatedly.


# 9. Further when we look at the material on record, it is an undisputed fact that the resolution plan in the present case was approved by the Adjudicating Authority beyond 330 days. Be that as it may, we also notice that the Adjudicating Authority had already approved the extension of CIRP period on 08.01.2024 which date was before 29.01.2024 when the plan was approved. In the present case, the 23rd CoC meeting on 04.12.2023 had taken note of the fact that it was in an advanced stage of considering the resolution plans before it and since the extended CIRP period was getting expired on 10.12.2023, the CoC approved seeking further extension of CIRP period. Clearly enough, CoC having taken a considered decision in this regard, this constituted sufficient grounds for the Adjudicating Authority to extend further time beyond 330 days for completion of the CIRP process. Hence, the judgment of the Hon’ble Supreme Court in Committee of Creditors of Essar Steel India Vs Satish Kumar Gupta in Civil Appeal No. 8766-67 of 2019 which has been relied upon by the Appellant does not come to their rescue since this judgment does not completely rule out the possibility of CIRP extension beyond 330 days particularly so when a short period is left for completion of CIRP.


# 10. In such circumstances, we are not persuaded to accept the contention of the Appellant that the resolution plan could not have been approved by the Adjudicating Authority since the CIRP timeline had stood exhausted.


# 11. Yet another perceived irregularity contended by the Appellant is that though Regulation 35(2) of the CIRP Regulations makes it incumbent on the part of the RP to provide fair value, liquidation value and valuation report to every member of the CoC, the same was not done.


# 12. To appreciate the above allegation better, we need to look at the minutes of the 17thCoC meeting wherein this issue was discussed in details which is as extracted hereunder:

  • “Agenda 7) Any other matters relevant to the present case subject to approval of Chairman.

  • One of the CoC members i.e. Riddhi Siddhi GlucoBiols Limited represented by their authorised representative required and insisted the RP to provide them the Valuation Reports of the Corporate Debtor to share ahead with prospective buyers.

  • The RP informed that he can only share the Fair Value & Liquidation Value of the Corporate Debtor. The RP drew their attention to the regulations of the IBC, 2016 that as per the Regulation 35(2) of the Insolvency and Bankruptcy Board of India (Insolvency Resolution Process for Corporate Persons) Regulations, 2016 which is quoted below:

  • “After the receipt of resolution plans in accordance with the Code and these regulations, the resolution professional shall provide the fair values and the liquidation value to every member of the committee in electronic form, on receiving an undertaking from the member to the effect that such member shall maintain confidentiality of the fair value and the liquidation value and shall not use such values to cause an undue gain or undue lass to itself or any other person and comply with the requirements under sub-section (2) of section 29”

  • The RP even informed the CoC members that such liquidation value and fair value were already sent and shared with all the CoC members. He further informed that CoC members also cannot share the values with anyone as they have provided the undertaking as per the Regulation 35(2) of the Insolvency and Bankruptcy Board of India (Insolvency Resolution Process for Corporate Persons) Regulations, 2016 and Section 29 of the Insolvency & Bankruptcy Code, 2016.”


# 13. When we look at the above 17th CoC meeting proceedings, we find that the issue of sharing of the detailed valuation report had been raised therein by this Appellant. We find that the CoC had considered this issue in the meeting and minuted the reasons for only sharing the bare figures of the fair value and liquidation value of the Corporate Debtor. Besides the fact that this matter was duly considered, deliberated and decided upon by the CoC in its commercial wisdom, it is also pertinent to note that since the Operational Creditor had no right to vote in the meeting of the CoC, they cannot be said to have suffered from any prejudice for not being provided with the valuation report. Whether the detailed valuation report was placed before the Appellant or not was immaterial since it was the members of the CoC who were required to exercise the commercial wisdom on the valuation reports placed before them and not the Appellant who did not have the right to exercise their vote. The bogey of non-sharing of the detailed valuation report as a ground evidencing material or procedural irregularity therefore lacks force.


3 14. Even the ground raised by the Appellant that Form-G had not been published on the websites of the Corporate Debtor and IBBI lacks force of contention since this is again another much belated complaint. It does not lie in their mouth to agitate this matter now when they had slept over this issue all along when the EoIs were received. Further, non-publication of Form-G has a bearing on the interests of the potential resolution applicants who have not raised any such complaint. The Appellant in their capacity as Operational Creditor cannot rightfully claim that their interests were prejudicially affected on this count. Moreover, it is ironical that on the one hand the Appellant has been expressing concern over CIRP timelines having been crossed and yet a belated complaint is being thrown up pushing the plan approval process into disarray.


# 15. Yet another contention of the Appellant was that the plan was wrongly approved by the Adjudicating Authority without the plan conforming to the statutory provision as contained in Section 30(2)(b) of the IBC. This argument was premised on the ground that the Appellant as Operational Creditor had not been allocated amount as per their entitlement under Section 30(2)(b) of IBC.


# 16. To decide on the tenability of the above argument, we may first notice the provisions contained in Section 30(2)(b) of the IBC which reads as follows:

  • Section 30: Submission of resolution plan.

  • 30. (2) The resolution professional shall examine each resolution plan received by him to confirm that each resolution plan—

  • (a) provides for the payment of insolvency resolution process costs in a manner specified by the Board in priority to the payment of other debts of the corporate debtor;

  • (b) provides for the payment of debts of operational creditors in such manner as may be specified by the Board which shall not be less than-

  • (i) the amount to be paid to such creditors in the event of a liquidation of the corporate debtor under section 53; or

  • (ii) the amount that would have been paid to such creditors, if the amount to be distributed under the resolution plan had been distributed in accordance with the order of priority in sub-section (1) of section 53, whichever is higher, and provides for the payment of debts of financial creditors, who do not vote in favour of the resolution plan, in such manner as may be specified by the Board, which shall not be less than the amount to be paid to such creditors in accordance with sub-section (1) of section 53 in the event of a liquidation of the corporate debtor.

  • Explanation 1.-For removal of doubts, it is hereby clarified that a distribution in accordance with the provisions of this clause shall be fair and equitable to such creditors.


# 17. From a plain reading of the above statutory provision, the entitlement of an Operational Creditor is to receive the amount as provided under Section 30(2)(b) of IBC which is not less than the amount which the Appellant would have been entitled to receive in the event of a liquidation of the Corporate Debtor under Section 53 of the IBC. When we see the material on record, we find that the fair value of the Corporate Debtor was Rs 45.85 Cr and the liquidation value was Rs 33.16 Cr with no amount specified for Operational Creditors. On the other hand, when we see the plan features at para 15 of the impugned order, the plan provides for Rs. 60 lakhs for Operational Creditors which sum was clearly more than the liquidation value which was their minimum entitlement. That being so, the resolution plan cannot be said to be in dissonance with the provisions of Section 30(2)(b) of IBC.


# 18. Furthermore, the resolution plan having been approved by more than 66% of vote share by the CoC, such plan cannot be interfered with by the Adjudicating Authority merely on the grounds that the Operational Creditors were being paid Rs 60 lakhs at a time when no amount has been specified for Operational Creditors in terms of liquidation value. We are of therefore of the considered view that since the liquidation value in the present case is nil, the Operational Creditors including the Appellant cannot have any grievance against the amount being paid to them since the amount paid under the plan to the Operational Creditors is clearly more than the liquidation value.


# 19. The resolution plan has been approved with a majority of 97.36% of vote share. The plan having been approved by majority of votes, the Operational Creditor is clearly bound by the approved resolution plan. We therefore are of the considered view that the Adjudicating Authority did not commit any error while approving the resolution plan after noting its satisfaction at para 26 of the impugned order about the plan being in compliance of the provisions of the IBC in terms of Section 30(2) of the IBC.


# 20. It may be useful to notice that Section 30 of the IBC which deals with submission of Resolution Plan and sub-section (6) thereto states that “the resolution professional shall submit the Resolution Plan as approved by the Committee of Creditors to the Adjudicating Authority”. In the present case, the RP after approval of the plan by the CoC with 97.36% vote share filed an application before the Adjudicating Authority seeking approval of the Resolution Plan under Section 31 of the Code. Section 31 deals with approval of Resolution Plan. Section 31(1) provides that if the Adjudicating Authority is satisfied that the Resolution Plan as approved by the CoC under Section 30(4) meets the requirements as referred to in Section 30(2), it shall by order approve the resolution plan which shall be binding on the Corporate Debtor and other stakeholders involved in the Resolution Plan. It is also pertinent to note that the Adjudicating Authority has noted at para 20 of the impugned order that the CoC has satisfied itself that the resolution plan meets the requirement of being viable and feasible for revival of the Corporate Debtor. That the CoC also expressed its satisfaction that the plan was in accordance with Section 30 of the IBC and compliant with CIRP Regulations 38 has been noticed at para 18 of the impugned order. Furthermore, the Adjudicating Authority has noticed at para 26 of the impugned order that the plan was in accordance with Sections 30 and 31 of the IBC and complies with Regulations 38 and 39 of CIRP Regulations.


# 21. Law is now well settled that the jurisdiction of the Adjudicating and Appellate Authorities to interfere with approval of the resolution plan is limited. The scope of judicial review is confined to the provisions contained in Section 30(2) of the IBC for the Adjudicating Authority and Section 30(2) read with Section 61(3) for the Appellate Authority. There is only limited review which can be exercised by the Adjudicating Authority or the Appellate Authority. There can be no fetters on the commercial wisdom of CoC. The supremacy of commercial wisdom of CoC has been reaffirmed time and again by the Hon’ble Supreme Court in a catena of judgements – 

  • K. Sashidhar v. Indian Overseas Bank (2019) 12 SCC 150 ; 

  • Committee of Creditors of Essar Steel India Limited v. Satish Kumar Gupta (2020) 8 SCC 531; 

  • Maharashtra Seamless Limited v. Padmanabhan Venkatesh (2020) 11 SCC 467; 

  • Kalpraj Dharamshi v. Kotak Investment Advisors Limited, (2021) 10 SCC 401 and 

  • Ghanashyam Mishra and Sons Private Limited through the Authorized Signatory v. Edelweiss Asset Reconstruction Company Limited through the Director (2021) 9 SCC 657.


# 22. So long the statutory provisions of the IBC and the CIRP Regulations framed thereunder are complied with, it is the commercial wisdom of the requisite majority of the CoC which is to negotiate and accept a resolution plan. Once all the mandatory requirements have been duly complied with and taken care of, judicial review cannot be extended to analyse and look into the dissatisfaction evinced by any particular creditor or stakeholder. The Adjudicating Authority cannot substitute its views with the commercial wisdom of the CoC nor deal with the merits of Resolution Plan unless it is found it to be contrary to the express provisions of law and against the public interest. There is neither any material irregularity nor contravention of any provisions of law by the CoC which has been justifiably substantiated by the Appellant. In the present case when no valid grounds have been made out to challenge the approval of the resolution plan, the legislative fiat of the IBC that the Adjudicating Authority cannot trespass upon the business decision of the CoC holds ground. We have no doubts in our mind that the plan has been rightly approved by the Adjudicating Authority.


# 23. In result, we do not find any good ground to interfere with the impugned order approving the resolution plan. There is no merit in the appeal. The Appeal is dismissed. No costs.

--------------------------------------------------------


Disclaimer:

The sole purpose of this post is to create awareness on the "IBC - Case Law" and to provide synopsis of the concerned case law, must not be used as a guide for taking or recommending any action or decision. A reader must refer to the full citation of the order & do one's own research and seek professional advice if he intends to take any action or decision in the matters covered in this post.