Tuesday, 30 January 2024

Assistant Commissioner, CGST & CX, Joka Division Vs M/s. Environ Energy Corporation India Private Limited, - We find no merit in the application made by the GST department on both counts (i.e.) extraordinary delay in submitting the claim before the liquidator which is 664 days from the date the claim ought to have been filed and delay in filing this appeal before the Adjudicating Authority which is nearly four months beyond the statutory time limit, prescribed under Section 42 of IBC.

 NCLT Kolkata (31.05.2005) in Assistant Commissioner, CGST & CX, Joka Division, Kolkata South Commissionerate Vs M/s. Environ Energy Corporation India Private Limited, [I.A. (IB) No. 1472/KB/ 2023 In CP (IB) No. 1106/KB/2019] held that;

  • We find no merit in the application made by the GST department on both counts (i.e.) extraordinary delay in submitting the claim before the liquidator which is 664 days from the date the claim ought to have been filed and delay in filing this appeal before the Adjudicating Authority which is nearly four months beyond the statutory time limit, prescribed under Section 42 of IBC.


Excerpts of the order;

# 3. This application has been preferred under Section 42 of the Insolvency and Bankruptcy Code, 2016 (IBC) by the Assistant Commissioner, CGST on Central Excise, Joka Division, Kolkata South Commissionerate, (hereinafter referred to as ‘Applicant / GST Department’) against M/s. Envaron Energy Corporation India Private Limited (in Liquidation) represented by its Official Liquidator Mr. Rakesh Kumar Agarwal (hereinafterreferred to as Corporate Debtor/Respondent).


# 4. Under Section 42 of the IBC, the Applicant has sought the following relief:

a) To direct the Official Liquidator to accept and consider the claim of the applicant;

b) Delay in preferring the instant applicant (if any), be condoned by this Tribunal for the interest of justice;

c) Delay of 664 days to prefer the claim before the Official Liquidator be condoned by this Tribunal for the interest of justice;

d) Accept the claim of the Applicant as mentioned in the Order-in-Originals stated in paragraph no. 2 hereinabove;

e) Such other and further order may be deemed fit and proper.


# 5. Factual Matrix:

5.1. The GST department had issued show cause notice and consequent orders in original Demanding Service Tax on the Corporate Debtor through 3 separate orders annexed as Annexures A1, A2 and A3 to the application.

5.2. The order in original dated 10.03.2017, annexed as Annexure A1 demanded a sum of Rs.5,11,56,977/- along with interest and penalty of Rs.5,11,56,977/-.

5.3. The Order in original dated 31.05.2018 issued by the GST Department, annexed as Annexure A2, demanded a sum of Rs.94,66,590/- along with interest and penalty of Rs.9,46,659/-.

5.4. The Order in original dated 03.05.2019 which is annexed as Annexure A3 has demanded a sum of Rs.1,42,49,024/- along with interest and penalty of Rs.14,24,902/-, apart from late fee of Rs.59,100/-. All these orders were served on the Corporate Debtor , claims the Applicant.

5.5. Subsequently, a show cause notice was served on the Corporate Debtor dated 28.06.2019 which is annexed as Annexure A4 demanding Rs.12,22,36,041/- along with interest, apart from proposing to levy a penalty of Rs. 22,22,36,041/-

5.6. In response to the said show cause notice, the Corporate Debtor through its Liquidator had replied by submitting the order of NCLT, Kolkata Bench 19th May of 2021 informing about the liquidation order passed and the same was attached as the response to the show cause notice dated 28.06.2019. 

5.7. The GST department claims that this response to the show cause notice was received only on 16.03.2023 and consequently, they lodged their claim in the prescribed Form B of IBBI (Liquidation Process Regulations, 2016) on 13.04.2023.

5.8. On 24.04.2023, the Applicant GST Department , received an e-mail from the liquidator of the Corporate Debtor informing that the Liquidation Process of the respondent company commenced on 19.05.2021 and the last date for filing the claim as per the public announcement made is 18th June 2021. The Official Liquidator, therefore, declined to admit the claim made by the Applicant on 13th April 2023, which is after a delay of 664 days. Consequent, to this e-mail received from the Liquidator on 24.04.2023 this application has been filed by the GST, Department on 30.08.2023 seeking the reliefs mentioned above.


# 6. Applicant’s Submission: -

6.1. The Learned Counsel for the appellant submits that they became aware of the liquidation of the company only on 16.03.2023 and immediately on becoming aware they filed the claim with the liquidator on 13.04.2023 in Form B as prescribed under the (IBBI), Liquidation Process Regulations, which is well within 30 days from the date of coming to the

know of the Liquidation. 

6.2. It is submitted that they were never informed about the commencement of Liquidation by the Corporate Debtor; therefore, this has resulted in a delay of 664 days to prefer the claim before the Liquidator

6.3. Considering that the revenue of more than 60 crores of rupees due to the National Exchequer is involved in this case, the delay in preferring this claim may be condoned under the above facts and circumstances and the Liquidator may be directed to admit the claim in the interest of revenue/nation.


# 7. Respondent’s Submission per contra: -

7.1. Learned Counsel for the Liquidator claims that the advertisement for inviting claim as per IBBI Liquidation Process Regulation, 2016 was made in Form B of Schedule II within 5 days from the date of order of liquidation by NCLT on 19.05.2021. The public announcement was made in two large English papers as well as in the vernacular newspapers. The public announcement called upon all the stakeholders to submit their claims within 30 days from the date of advertisement.

7.2. As per Regulation 17 of the IBBI (Liquidation process) Regulation an Operational Creditor like GST Department will have to submit proof of the claim to the liquidator in the prescribed form with relevant documents to prove their claim.

7.3. The Regulation also provides that in case the OperationalCreditor has submitted its claim during the CIR process the same shall be deemed to submitted under Section 38 of IBC which is the section that governs the submission of claims before the liquidator. Having not done so the Operational Creditor/GST department has lost the opportunity to submit their claim at this stage when liquidation is at the far end of the process.


# 8. Analysis and Findings:

8.1. As per the pleading and records placed in the application, we find that the Orders passed by the GST department are with reference to the demands made under the erstwhile service tax regime.

8.2. As per Section 87 of the Finance Act, 1994 (which govern the Levy and Collection of Service Tax) for Recovery of any amount due to the Central Government there is a recovery mechanism which includes attachment of the Bank Accounts/ moveable and immoveable properties etc. and the same can be done and such attached properties can be sold and dues to the Government could be recovered.

8.3. In the given case nothing has been placed on record by the GST department that such recovery proceedings have been initiated for the recovery of such huge sums to the exchequer. In the absence of any such action placed on record, we will have to infer that no such action has been taken by the GST department. Having failed to do so they should have at least submitted their claim before the Resolution Professional during CIRP of the Corporate Debtor. Nothing has been placed on record to suggest that the GST department has submitted their claims during the CIR process with the Resolution Professional.

8.4. Thus, they failed to take any action even during the CIR process. GST Department cannot claim ignorance of the commencement of CIRP of its own assessee, from whom large sums are due when such proceedings are made public at large by way of public announcement in newspapers apart from the announcement in the Insolvency Bankruptcy Board of India, website.

8.5. The regulations made under IBBI do not provide for individual communication to creditors about the CIRP process or Liquidation Process as the same would delay the entire time-bound CIRP/Liquidation process. That is why we are of the view that the law has prescribed for public announcements in large newspapers.

8.6. Therefore, the claim of the department that they were not aware of the CIRP proceedings/liquidation proceedings cannot be accepted particularly when the department interacts with the assessee on a monthly basis through several Returns.

8.7. In this case, they claim that they became aware when they received the response of the Corporate Debtor against the show cause notice dated 28.06.2019. The show cause notice dated 28.06.2019 would have been served within 10 days from the date of notice. Assuming that this was served during 1st week of July 2019, the response from the Corporate Debtor would have been received within 30 days from the receipt of show cause notice, as show cause notice mandates reply from the Corporate Debtor within 30 days from the receipt of show cause notice. If no such reply was received, GST Department can pass an ex-parte order after granting a hearing. Nothing of that sort has been done as per the records placed.

8.8. It is not the claim of the department that the Applicant received the notice dated 28.06.2019 only in 2023, and consequently they received the response from the Applicant only 16.03.2023. We see only delays and latches writ large on the part of the GST department.

8.9. The rejection letter from the liquidator through email was received on 24.04.2023, whereas this appeal has been preferred before NCLT on 30.08.2023. As per Section 42 of the IBC, the stakeholders will have to file an appeal to the Adjudicating Authority against the decision of the Liquidator within 14 days of the receipt of such decision. In this case, they claim to have received the rejection on 24.04.2023. In that case statutory time limit for preferring appeal before this Adjudicating Authority ends on 8th May 2023.

8.10. Even in preferring an appeal they have taken nearly another four months beyond the statutory limit prescribed in IBC and filed it only on 30.08.2023. This clearly demonstrates the lackadaisical approach of the GST department in pursuing such large demands from the Corporate Debtor.

8.11. In view of the above, we find no merit in the application made by the GST department on both counts (i.e.) extraordinary delay in submitting the claim before the liquidator which is 664 days from the date the claim ought to have been filed and delay in filing this appeal before the Adjudicating Authority which is nearly four months beyond the statutory time limit, prescribed under Section 42 of IBC.

8.12. The Legal Positions:

a. In The Deputy Commissioner Commercial Taxes (Audit), Raichur -Vs-Surana Industries Ltd. (In Liquidation) & Anr. in Company Appeal (AT) (Insolvency) No. 1525 of 2019 dated 07.02.2020, wherein the Hon'ble NCLAT has dismissed the application filed by the Applicant in relation to the Appeal against the order of the Liquidator and also held that liquidation process is a time bound process, and the Liquidator has to conclude his proceedings within one year. (Emphasis supplied)

b. Further, we are fortified by the decision of a Coordinate Bench. NCLT, Chennai Bench in the matter of Employees State Insurance Corporation vs. Chinnam Poorna Chandra Rao reported in [2020] ibclaw.in 180 NCLAT where it was held that the extraordinary delay [] in submission of claim by applicant, is devoid of merits. Further in interest of Justice also we could not condone the delay as sought for. If such extraordinary delay is condoned, it shall defeat the very purpose of the IBC, 2016. (Emphasis supplied)


# 9. In the view foregoing, we dismiss this application being I.A. (IB) No.1472/KB/2023 in Company Petition (IB) No. 1106/KB/2019 accordingly.


# 10. No cost upon the applicant herein.

\

# 11. Certified copies of the order, if applied for with the Registry of this Adjudicating Authority, be supplied to the parties upon compliance with all requisite formalities.


-------------------------------------------------------


Monday, 29 January 2024

Mr. Anuj Sharma Vs. Rustagi Projects Pvt. Ltd. - It is, therefore, clear from these facts that the total amount for maintainability of claim will include both principal debt amount as well as interest on delayed payment which was clearly stipulated in the invoice itself.

 NCLAT (04.07.2023) in Mr. Anuj Sharma Vs. Rustagi Projects Pvt. Ltd. [Company Appeal (AT) (Insolvency) No.550 of 2023] held that;

  • That the debt includes both Principal and Interest, which position of law has been settled by this Tribunal by its judgment in “Company Appeal (AT) (Ins.) No. 690 of 2022, Prashant Agarwal vs. Vikash Parasrampuria & Anr.”

  • That the total amount for maintainability of claim will include both principal debt amount as well as interest on delayed payment which is stipulated in the invoice has to be added.

  • It is, therefore, clear from these facts that the total amount for maintainability of claim will include both principal debt amount as well as interest on delayed payment which was clearly stipulated in the invoice itself. 

  • That for calculating the amount for maintainability of the claim, for threshold purpose, both Principal Amount and Interest has to be calculated when the interest is stipulated between the parties.


Excerpts of the order;

This Appeal by Suspended Director of the Corporate Debtor has been filed challenging the order dated 26.04.2023 passed by the Adjudicating Authority (National Company Law Tribunal), New Delhi, Court-III by which order, Section 9 application filed by the Operational Creditor (Respondent herein) has been admitted. Brief facts of the case necessary to be noticed for deciding this Appeal are:

i. Corporate Debtor and Operational Creditor entered into Distributorship Agreement dated 20.07.2016. The Distributorship Agreement contained Terms of Payment and Delivery. The Corporate Debtor was engaged in the manufacturing, market training, sale, purchase, imports, exports, distribution or otherwise dealing in all types of battery-operated vehicle, batteries, its parts and accessories including those manufactured / sold by other manufacturers / companies.

ii. The Operational Creditor issued various purchase orders and made certain payment from time to time. Purchase Order contained a condition that “Delivery should be done within 90 days, otherwise advance shall be returned along with interest @18% p.a”. Appellant – Operational Creditor made certain advance payments.

iii. The Operational Creditor sent emails dated 16.06.2018 demanding an amount of Rs.58,49,800/-. Further email was sent on 26.07.2018 demanding amount of Rs.60,24,800/- which included interest of Rs.7,80,000/-.

iv. Operational Creditor issued a demand notice under Section 8 dated 21.12.2020 claiming Principal Amount of Rs.56,63,061/- with interest amount of Rs.66,03,801/- and expenses totalling to Rs.1,34,69,435/-. Demand Notice was served on the Corporate Debtor but no reply was filed.

v. An application under Section 9 was filed by the Operational Creditor claiming total operational debt of Rs.1,34,69,435/-. Adjudicating Authority issued notice on 09.08.2021. The Corporate Debtor appeared on 10.01.2022 and prayed for two weeks’ time to file reply in the matter which was allowed. Again on 14.02.2022, two weeks’ time was allowed to file reply. Thereafter, several dates were fixed, on which adjournment was sought by the Corporate Debtor on ground that judgment of this Tribunal in “M/s. Jumbo Paper Products Ltd. vs. Hansraj Agro fresh Private Limited is pending in the Hon’ble Supreme Court for consideration, which adjournment was allowed.

vi. I.A. No. 1891 of 2022 was filed by the Corporate Debtor praying for dismissal of the Company Petition filed by the Operational Creditor. I.A. No. 1891 of 2022 filed by the Corporate Debtor came to be dismissed for non-prosecution on 21.10.2022.

vii. On 13.12.2022, learned counsel for the Operational Creditor appeared but neither Corporate Debtor appeared not filed any reply. Corporate Debtor was directed to proceed ex-parte.

viii. Matter was heard by the Adjudicating Authority on 29.03.2023 and order was reserved. Adjudicating Authority vide the impugned order dated 26.04.2023 admitted Section 9 application. The Adjudicating Authority held in the order that debt and default is proved and Corporate Debtor failed to repay the amount. Hence, the application is admitted.

ix. The Corporate Debtor has filed an I.A. on 03.03.2023 for recall of order dated 21.10.2022 and 13.12.2022 passed by the Adjudicating Authority. Aggrieved by the order dated 26.04.2023, this appeal has been filed.


# 2. We have heard Shri Aditya Nayyar, learned counsel for the Appellant and Shri Hamid Ahmad, learned counsel appearing for Respondent No.1 – Operational Creditor.


# 3. Learned counsel for the Appellant submits that the Adjudicating Authority has adjourned the matter twice taking note of the fact that judgment of this Tribunal in “Jumbo Paper Products Ltd.” is pending consideration before the Hon’ble Supreme Court. The Adjudicating Authority ought to have awaited orders of the Hon’ble Supreme Court. It is submitted that according to own case of the Operational Creditor the Principal Amount due was only Rs.56,63,061/- and interest amount was of Rs.66,03,801/-. The amount of interest was not liable to be added and threshold of Rs.1 crore was not fulfilled whereas application was filed after 24.03.2020, hence, it deserves to be dismissed on this ground. The Corporate Debtor had filed an application on the ground that it does not fulfil the threshold, which application was unfortunately dismissed for non-prosecution since the counsel for the Corporate Debtor could not appear on 21.10.2022. Appellant has also filed an application for recall of the order dated 21.10.2022 as well as order dated 13.12.2022, where the Adjudicating Authority directed to proceed ex-parte to the Corporate Debtor, which application remained pending and could not be listed. It is submitted that submission of the Respondent that no vehicles were supplied is incorrect. It is submitted that Purchase Orders did not contain any clause for payment of interest and Purchase Orders annexed with Section 9 application were false. In the application which is filed by the Corporate Debtor being I.A. No. 1891 of 2022 ground of Section 10A was also taken since the demand notice was issued on 24.12.2020 and application was barred by 10A.


# 4. Learned counsel appearing for the Respondent No.1 submits that the reliance of the Appellant on the judgment of this Tribunal in M/s. Jumbo Paper Products Ltd. vs. Hansraj Agro fresh Private Limited has no application in the facts of the present case. There cannot be any dispute that after 24.03.2020 every application filed under Section 9 has to fulfil the threshold of Rs.1 Crore. In the present case, by the demand notice and Section 9 application the operational debt claimed by the Appellant was more than Rs.1 Crore. The Purchase Order included condition that if the goods are not supplied within 90 days, the advance shall be refunded with 18% interest p.a. It is submitted that the debt includes both Principal and Interest, which position of law has been settled by this Tribunal by its judgment in “Company Appeal (AT) (Ins.) No. 690 of 2022, Prashant Agarwal vs. Vikash Parasrampuria & Anr.”. It is submitted that the Operational Creditor sent various emails in 2018 itself demanding back the amount, which emails contain both claim for Principal Amount as well as the Interest. Various WhatsApp Chats were also annexed along with Section 9 application to indicate that the Operational Creditor has been demanding the refund from time to time. It is submitted that the Appellant has been dragging the proceedings before the Adjudicating Authority and out of 15 dates which were fixed before the Adjudicating Authority, the Appellant appeared only on few dates and despite taking time from the Adjudicating Authority on several occasions no reply was filed by the Corporate Debtor. The Corporate Debtor to avoid the payment to the Operational Creditor has been dragging the proceeding. The Adjudicating Authority has rightly proceeded ex-parte against the Corporate Debtor since neither he filed reply nor he appeared on the date fixed. It is submitted that the application filed by the Corporate Debtor to recall the order dated 21.10.2022 and 13.12.2022 were without any basis. The Corporate Debtor was not entitled for any indulgence in view of the conduct of the Corporate Debtor during the entire proceeding which remained pending for two years.


# 5. We have considered the submissions of learned counsel for the parties and perused the record.


# 6. Part IV of the application which is ‘Particulars of Operational Debt’ provides as follows:

PARTICULARS OF OPERATIONAL DEBT

1.

TOTAL AMOUNT OF DEBT

The total amount of debt payable by the Corporate Debtor to Operational Creditor is Rs.56,63,061 (Fifty Six Lakh sixty three thousand and Sixty One) and the total amount of Interest due and payable on unpaid Operational Debt as on 25th December, 2020 is 66,03,801/ (Rupees Sixty Six Lakhs Three Thousand Eight Hundred And One/-) (Including GST 18%) and such further Interest @ 18 as would be due for the payment after 25th December, 2020 till the date of realization of the unpaid Operational Debt and expenses incurred towards the advertisement Rs.7,02,573/- legal charges of Rs.5,00,000/-.

Hence, the Aggregate of total amount of unpaid Operational Debt due and payable by the Corporate Debtor to the Operational Creditor as on 25th December, 2020 is Rs 1,34,69,435/- (Rupees One Crore Thirty Four Lakhs Sixty Nine Thousand Four Thirty Five Only).


# 7. In Part IV at Serial No.2 ‘amount claimed to be in default and the date on which the default occurred’ is mentioned as follows:

2.

AMOUNT CLAIMED TO BE IN DEFAULT  AND THE DATE ONWHICH THE DEFAULT OCCURRED (ATTACH THE WORKINGSFOR COMPUTATI ON OF AMOUNT AND DAYS OF DEFAULT IN TABULAR FORM)

The total amount of debt payable by the Corporate Debtor to Operational Creditor is Rs.56,63,061 (Fifty Six Lakh sixty three thousand and Sixty One) and the total amount of Interest due and payable on unpaid Operational Debt as on 25th December, 2020 is 66,03,801/ (Rupees Sixty Six Lakhs Three Thousand Eight Hundred And One/-) (Including GST @ 9% and CGST @ 9%) and such further Interest @ 18 as would be due for the payment after 25th December, 2020 till the date of realization of the unpaid Operational Debt and expenses incurred towards the advertisement Rs.7,02,573/- legal charges of Rs.5,00,000/-.

Hence, the Aggregate of total amount of unpaid Operational Debt due and payable by the Corporate Debtor to the Operational Creditor as on 25th December, 2020 is Rs 1,34,69,435/- (Rupees One Crore Thirty Four Lakhs Sixty Nine Thousand Four Thirty Five Only).

The computation of amount of default and date of default has been attached herewith as ANNEXURE XIII.

Date of Default:- 26/7/2018 and its continues one


# 8. The claim of the Operational Creditor as reflected from Part IV of the application indicate that total claim is more than Rs.1 Crore which include the Principal Amount of Rs.56,63,061/- and interest. The Operational Creditor has brought on record the Purchase Orders dated 05.05.2017, 06.05.2017, 14.08.2017 and 12.11.2016. We may refer to Purchase Order dated 06.05.2017 where following terms and conditions have been mentioned:

  • “TERMS & CONDITIONS:

  • 1) Delivery should be done with in 90 days, otherwise advance shall be returned along with interest @ 18% p.a.

  • 2) Transportation cost extra at actual.

  • 3) All bills should be sent t0 Rustagi projects Pvt Ltd. Kalyan address only.


# 9. We may also notice the emails which have been sent by the Operational Creditor to the Corporate Debtor demanding the payment. The emails which have been sent by the Operational Creditor, which have been brought on the record along with the Reply filed in this Appeal, indicate that the claim contains Principal Amount as well as interest as was due on the date when email was sent. It is useful to extract one of the emails dated 26.07.2018 sent to the Corporate Debtor, which is to the following effect:

“Re: Demand of Rupees 60,74,800 till date or E-Loaders of Equivalant amount in lieu thereof:
From: Rajesh Yadav (rajesh@rustagi.info)
To: anuj.sh99@gmail.com
Cc jai.bagga@gmail.com; vikrampugalia@rediffmail.com;
sgupta34@yahoo.co.in; sonilvehicle@gmail.com;
info@sonivehicle.com; sonicustomercare@ gmail.com
Date: Thursday, July 26,2018,03:18 PM GMT+5:30

Dear Sir

Given below is the detail of amounts outstanding against your account in our books till today.

We request you to take immediate steps to return / refund our amount with Interest or you can send us the E-loaders of equivalent amount till 31st July’ 2018 and oblige.

Initially Paid to you : 50,00,000/-
Interest Till 31/07/2018 : 7,80,000/-
Returned 88 Batteries Refund : 2,94,800/-
__________________________________________________
Total Till date:- :60,74,800

Kindly make the Payment on priority.

Regards
Rajesh Y
Rustagi Projects Pvt Ltd.”


# 10. Learned counsel for the Appellant before us has submitted that the Purchase Orders which was issued does not contain any condition for payment of interest. Copy of the Purchase Orders were part of the Section 9 application which clearly contain the condition of interest. Furthermore, in the email which was sent by the Operational Creditor in the year 2018, the amount of interest was also included. The Corporate Debtor did not file any reply to the Section 9 application although twice the time was taken for filing reply. On 10.01.2022, the Adjudicating Authority granted two weeks’ time to file reply by following order:

  • “ORDER

  • Counsels for both sides are present. Counsel appearing on behalf of the Corporate Debtor seeks two weeks’ time to file reply in the matter. The time prayed for is granted. List the matter on 14.2.2022.”


# 11. Further on 14.02.2022, another order was passed granting two weeks’ time to the Appellant to file reply. Order dated 14.02.2022 is as follows:

  • “ORDER

  • Mr. Hamid Ahamd Mir, Counsel for the Petitioner/ Operational Creditor is present. Mr. Mohit Arora, Counsel for the Corporate Debtor has also appeared and submits that he is yet to file Vakalatnama in the matter. He is directed to do the needful within two days’ time.

  • In addition, Counsel for the Corporate Debtor is also directed to file reply on behalf of his client within two weeks with a copy to be made available to Counsel for the petitioner. Counsel for the Operational Creditor to file rejoinder, if any, within a week.

  • List on 10.3.2022.”


# 12. The Corporate Debtor chose not to file reply and filed an I.A. for dismissing the application under Section 9. I.A. which was filed by the Appellant was dismissed for non-prosecution. We may also look into the grounds taken in the I.A. for dismissing the Company Petition. In the I.A. the ground taken was that the interest component cannot be added in the Operational Debt. Further Section 10A of the Code was relied referring to Demand Notice dated 21.12.2020.


# 13. Learned counsel for the Operational Creditor has rightly relied on judgment of this Tribunal in “Company Appeal (AT) (Ins.) No. 690 of 2022, Prashant Agarwal vs. Vikash Parasrampuria & Anr.”, where three Member Bench of this Tribunal held that the total amount for maintainability of claim will include both principal debt amount as well as interest on delayed payment which is stipulated in the invoice has to be added. We may refer to Para 9 (vi) of the judgment, which is to the following effect:

  • “9(vi) It is, therefore, clear from these facts that the total amount for maintainability of claim will include both principal debt amount as well as interest on delayed payment which was clearly stipulated in the invoice itself. It is noted that the total principal debt amount of Rs. 97,87,220/- along with interest the total debt makes total outstanding as Rs. 1,60,87,838/-. Thus, the total debt outstanding of OC is above Rs. 1 crore as per requirement of Section 4 IBC read with notification No. S.O I205 (E) dated 24.3.2020 (Supra), and meets the criteria of Rs.1 crore as per Section 4 of IBC and Application is therefore maintainable in present case.

  • We concur with the orders of Adjudicating Authority on this issue also.”


# 14. The above judgment of “Prashant Agarwal” clearly supports the submission of learned counsel for the Respondent that for calculating the amount for maintainability of the claim, for threshold purpose, both Principal Amount and Interest has to be calculated when the interest is stipulated between the parties.


# 15. The ground taken in the I.A. under 10A is clearly misconstrued since the default is being claimed by the Operational Creditor w.e.f. 26.07.2018 which was much before the 10A period. The mere fact that the Demand Notice was dated 21.12.2020 shall not has any effect on the maintainability of the application under Section 9 when default is committed on 26.07.2018 and admitted thereafter.


# 16. In the facts of the present case, we are satisfied that the Adjudicating Authority did not commit any error in admitting Section 9 application which clearly fulfils the threshold. The Corporate Debtor despite having been allowed time, failed to file reply and did not appear on the date when matter was fixed for hearing. The Adjudicating Authority rightly proceeded ex-parte against the Corporate Debtor when he chose not to file reply and failed to appear on the date fixed. No error has been committed by the Adjudicating Authority in admitting Section 9 application. There is no merit in the Appeal. Appeal is dismissed.


-------------------------------------------------------


Disclaimer:

The sole purpose of this post is to create awareness on the "IBC - Case Law" and to provide synopsis of the concerned case law, must not be used as a guide for taking or recommending any action or decision. A reader must refer to the full citation of the order & do one's own research and seek professional advice if he intends to take any action or decision in the matters covered in this post.

Imp. Rulings - Guarantor’s Right of Subrogation

  Imp. Rulings - Guarantor’s Right of Subrogation Index; SCI (2024.07.23) in BRS Ventures Investments Ltd. Vs. SREI Infrastructure Finance L...