Wednesday 31 July 2024

Ms. Mausumi Bhattacharjee vs. Jumbo Chemicals and Allied Industries Pvt. Ltd. and Anr. - The question whether a subsequent agreement is an additional to the main agreement or not; as well as the fact whether new contract supercede old contract would depend on the facts and circumstances of each case.

 NCLAT (2024.07.02) in Ms. Mausumi Bhattacharjee vs. Jumbo Chemicals and Allied Industries Pvt. Ltd. and Anr. [(2024) ibclaw.in 422 NCLAT, Comp. App. (AT) (Ins) No. 886 of 2024 & I.A. No. 3196 of 2024] held that; 

  • That the requisites of a novation may include elements like an agreement of all the parties to a new contract, the extinguishment of the old obligations, and the validity in supersession of old contract by the new contract,

  • That if the contract is altered in material particulars to change its essential character, the modified contract must be read as doing away with the original contract but if the modified contract has no independent contractual force, no new contract comes into play.

  • The question whether a subsequent agreement is an additional to the main agreement or not; as well as the fact whether new contract supercede old contract would depend on the facts and circumstances of each case.


Excerpts of the order;

# 1. The present Appeal has been filed by Ms. Mausumi Bhattacharjee the Promoter of Arjun Industries Limited (in short Appellant) Ms. Mausumi Bhattacharjee who is the Shareholder and Suspended Board of Director of Arjun Industries Limited (in short Corporate Debtor) under Section 61(1) of the Insolvency & Bankruptcy Code, 2016 (in short ‘Code’) in Company Appeal (AT) (Insolvency) No. 886 of 2024 against the Impugned Order dated 22.02.2024 passed by the National Company Law Tribunal, New Delhi Bench (Court – II) (in short ‘Adjudicating Authority’) in IB-79/ND/2022, whereby an application was filed under Section 7 of the Code by the Respondent No. 1 was considered and Corporate Insolvency Resolution Process (in short CIRP) of the Corporate Debtor was initiated. Jumbo Chemicals and Allied Industries Private Limited is the Respondent No. 1 here who is Financial Creditor of the Corporate Debtor.


# 2. Heard the Counsel for the Parties and perused the records made available including the cited judgements.


# 3. It has been brought out that the Corporate Debtor availed a loan from Industrial Development Bank of India (in short IDBI) of Rs. 3.67 Crores and further entered into agreement for foreign currency loan for Rs. 1.83 Crores. It has been alleged by the Appellant that the entire problem of the Corporate Debtor began since the IDBI release only Rs. 3.29 Crores against sanction loan of Rs. 3.67 Crores and similarly release only Rs. 1.25 Crores (Foreign Currency Loan) against Rs. 1.83 Crores.


# 4. The Appellant could not service the debt and repay the loan and IDBI issued legal notice on 10.06.1998. The IDBI also filed OA No. 445/1998 before Debt Recovery Tribunal (in short DRT) for recovery of outstanding amount of Rs. 6,19,87,815/- and the Corporate Debtor, during pendency of such proceedings before DRT, approached IDBI for One Time Settlement (in short OTS) and agreed to settle the outstanding at Rs. 2.50 Crores.


# 5. It has been submitted that the Appellant could not pay even the OTS amount and thus OTS failed. The IDBI assigned its outstanding debts to Kotak Mahindra Bank Ltd. on 31.06.2006 and Kotak Mahindra Bank Ltd. further assigned the debt to the Respondent No. 1 on 16.04.2008 by registered deed ofassignment. Thus, the Respondent No. 1 became the Financial Creditor of the Corporate Debtor.


# 6. It was brought out that the Corporate Debtor filed a Writ Petition before the Hon’ble Delhi High Court for restraining the assignment of loan which was dismissed.


# 7. We note that the Respondent No. 1 filed a petition before the Hon’ble Delhi High Court for winding up of the Corporate Debtor under Section 433 (e) and 433 (f) and Section 434 r/w Section 439 of Companies Act, 1956 before Single Judge Bench. From the judgement delivered by the Hon’ble Delhi High Court dated 22.05.2014, it is observed that at one time the Delhi High Court asked the Appellant to deposit Rs. 2.5 Crores with the Registry, however, while dismissing the petition for winding up of the Corporate Debtor, the said amount of Rs. 2.5 Crores was ordered to be refunded. The Respondent No. 1 challenged Single Bench Judgement before the Division Bench of Delhi High Court for winding up of the Corporate Debtor which was also dismissed on 02.03.2016.

At this stage, it would be worth noting that these proceedings happened prior to Code came into force.


# 8. It has been brought out that a meeting was held between the Appellant and the Respondent No. 1 on 12.10.2018 for agreement on disinvestment of mortgaged properties of the Corporate Debtor and based on this meeting, the Appellant and the Respondent No. 1 entered into a settlement agreement on 27.08.2019, whereby it was agreed between the parties to sale the mortgaged properties and divide the proceed of the sale between them.


# 9. At this stage, we would like to take into account the settlement deed dated 27.08.2019 which reads as under :- . .  . 


# 10. From above settlement agreement, it is seen that parties accepted that the Appellant defaulted repayment of both rupee as well as foreign currency loan. The settlement agreement also note that the original loan of IDBI was assigned through Kotak Mahindra Bank Ltd. vide assignment deed dated 31.03.2006 who in turn further assigned the loan to the Respondent No. 1 vide assignment deed dated 16.04.2008.


# 11. The Settlement Agreement dated 27.08.2019 also stated that the parties have seen several rounds of litigations at different fora and substantial period has elapsed and therefore in order to settle the issues and disputes, it was agreed to sell the property bearing No. SP3-11(B) 1 & 2, Khuskhera Industrial Area, Khuskhera, District Alwar, Rajasthan by executing proposed tripartite agreement with proposed buyers at mutually decided price and subsequently distribute the sale proceeds into equal proportion between the Appellant of the Respondent No. 1.


# 12. It has been alleged that the Appellant sent an e-mail on 26.07.2021 cancelling the settlement agreement which was replied by the Respondent No. 1 on 04.08.2021 alleging that the Appellant is trying to escape his liabilities to repay the loan to the Respondent No. 1 by way of unilateral suo-moto cancellation of the settlement agreement dated 27.08.2019 which was not permissible.


# 13. The Respondent No. 1 filed an application under Section 7 of the Code before the Adjudicating Authority, which was allowed and the Corporate Debtor came into CIRP w.e.f. 22.02.2024.


# 14. The Appellant submitted that Section 62 of the Contract Act, 1872 provides that if parties to a contract agree to substitute a new contract for it, the original contract need not be performed. The Appellant stated that there was novation of contract and the old contract, therefore, ceased to exist between the Corporate Debtor and the Respondent No. 1. The Appellant also argued that in the present case, the Settlement Agreement dated 27.08.2019 did not mention any ‘financial debt’, which the Corporate Debtor allegedly ‘defaulted’ and remained payable and therefore at best the settlement agreement dated 27.08.2019 was a simpliciter agreement to sell the mortgaged properties. It is the case of the Appellant that reciprocal promises, alleged breach thereof, on account of its cancellation cannot constitute default under section 3(12) of the Code and therefore no application under Section 7 of the Code could have been filed for enforcement/ specific performance of such agreement to sell.


# 15. It is the case of the Appellant that in absence of any agreement or contract, there is no question of any debt or default on the part of the Corporate Debtor. It is further the case of the Appellant that the Impugned Order is perverse and need to be set aside.


# 16. The Appellant alleged that the Respondent No. 1 fraudulently concealed from Corporate Debtor that Respondent No. 1 was not an existing company as it’s name had been struck off from the Register of Companies under Section 248 (5), Companies Act, 2013 by Notification dated 08.08.2018. The Appellant further alleged that the Respondent No. 1 preferred Section 7 of the Code application without being in existence and therefore the whole exercise is abuse of process of law.


# 17. The Appellant submitted that the Adjudicating Authority erred in passing the Impugned Order since the Respondent No. 1 did not have any legal existence.


# 18. The Appellant elaborated that the Respondent No. 1 i.e., Jumbo Chemicals and Allied Industries Private Limited’s name got struck off on 08.08.2018 by the Ministry of Corporate Affair. The Appellant submitted that subsequently an alleged agreement was executed between the Corporate Debtor and the Respondent No. 1 on 27.08.2019 which was void. The Appellant stated that the Corporate Debtor vide email dated 26.07.2021 cancelled the said agreement on account of the non existence of legal entity of the Respondent No. 1, being struck off its name and not remaining as a legal entity in the eyes of law at the time of execution of agreement


# 19. The Respondent No. 1 submitted that on 18.09.2023, this Appellate Tribunal in the earlier round of litigation between the parties had held that the acknowledgment of debt in the balance sheets from 1998-99 is continuous and dismissed the argument of the Corporate Debtor based on the judgment rendered by the single judge of the Hon’ble Delhi High Court dated 22.05.2015 wherein it was held that the Financial Creditor has confined its claim only to a sum of Rs. 250 Lacs and interest thereon. The relevant part of this Appellate Tribunal’s earlier order dated 18.09.2023 reads as follows:

“21. When the Company Petition was dismissed with the observation as observed, we fail to see that how the Respondent can contend that claim of the Appellant is limited to only Rs. 250 Lakhs.”


# 20. It is the case of the Respondent No. 1 that this Appellate Tribunal while allowing the Appeal filed by the Respondent No. 1 had held that the Adjudicating Authority committed error in rejecting Section 7 Application filed by the Respondent No. 1 as barred by time.


# 21. The Respondent No. 1 alleged that the Appellant failed to bring out all relevant facts including the balance sheets relevant for the disposal of the Appeal and is trying to mislead this Appellate Tribunal in the present appeal.


# 22. The Respondent No. 1 refuted the plea of the Appellant about novation of contract and also refuted the plea of the Appellant that the Settlement Agreement dated 27.08.2019 modified the earlier contracts between the parties and was in supersession to all earlier contracts. The Respondent No. 1 submitted that the Settlement Agreement dated 27.08.2019 is not any modification or a novation of earlier Agreements i.e. Rupee Term Loan and Foreign Currency Loan. The Respondent No. 1 clarified that the Settlement Agreement was arrived at between the parties after long pending multiple cases filed by the Financial Creditor for realization of the loan amount and it was agreed that the mortgaged properties of the Corporate Debtor would be sold to settle the loan amount in full. The Respondent No. 1 also stated that the Settlement Agreement nowhere stated that the Settlement Agreement shall supersede or modify the loan agreements.


# 23. The Respondent No. 1 pleaded that the original loan/ assignment deed remain valid and continues and the Settlement Agreement dated 27.08.2019 is merely a mechanism to find a way to settle outstanding dues of the Respondent No. 1 and therefore it is not novation of existing legal contracts.


# 24. The Respondent No. 1 argued that the Section 62 of the Indian Contract Act, 1872 relied by the Appellant is not relevant here as the pre-requisite is substitution of the earlier contract which is not reflected in the contents of the Settlement Agreement. The Respondent No. 1 further stated that no intention on the part of the Appellant and the Respondent No. 1 for any novation resulting into modification/substitution of earlier loan agreement or assignment deed can be seen in the settlement agreement dated 27.08.2019.


# 25. We note that the requisites of a novation may include elements like an agreement of all the parties to a new contract, the extinguishment of the old obligations, and the validity in supersession of old contract by the new contract, however, in the present case no such specific clauses exist. We also note that the Settlement Agreement dated 27.08.2019 was only with regard to disposal of the mortgaged properties of the Corporate Debtor.


# 26. We will examine the pleading of the Appellant that since name of the Respondent No. 1 was struck off on the relevant date of signing of settlement agreement dated 27.08.2019, therefore there was no valid settlement agreement. We note that the name of Respondent no. 1 was struck off since the Respondent No. 1 could not furnish the financial statements to relevant authority on time, however, the same was restored by the National Company Law Tribunal, Bench-IV, New Delhi (in short ‘Tribunal’) vide its order dated 24.03.2021 passed in Appeal No. 533/252/ND/2019. The relevant portion of the order is reproduced as under :-

  • “10. ***The name of the petitioner company shall then stand restored in the Register of the Registrar of Companies (RoC) as if its name of the company had not been struck off.” (Emphasis Supplied)


# 27. It is significant to note that the Tribunal specifically mentioned the name of the Respondent No. 1 is restored as if its name had not been struck off. We note that the legal implication of this would be that all action taken by the Respondent No. 1 would remain valid including signing of the settlement agreement dated 27.08.2019 and therefore the pleadings of the Appellant on this ground stand rejected.


# 28. We understand that if the contract is altered in material particulars to change its essential character, the modified contract must be read as doing away with the original contract but if the modified contract has no independent contractual force, no new contract comes into play. We do not find any such wording in settlement agreement dated 27.08.2019


# 29. The question whether a subsequent agreement is an additional to the main agreement or not; as well as the fact whether new contract supercede old contract would depend on the facts and circumstances of each case. In the present case based on fact and circumstances brought out on record before us, we do not find that old loan agreements or assignment deeds ceased to exist by signing settlement agreement dated 27.08.2019 and therefore we are unable to accept the pleadings of the Appellant that Section 62 of the Indian Contract Act, 1872 will come into play in the present appeal.


# 30. We find that in case of Manohur Koyal vs. Thakur Das Naskar [(1888) 15 Cal 319], the plaintiff sued the defendant to recover Rs. 1100 due on a bond and after the due date of the bond, the plaintiff agreed to accept from the defendant, in satisfaction of the bond, Rs. 400/- in cash and a fresh bond for Rs. 700/-. The defendant failed to pay the Rs. 400 and to give the fresh bond of Rs. 700/-. In a suit by the plaintiff to recover the amount of original bond, the defendant contended that the subsequent agreement was a novation. It was held that Section 62 did not apply, as the subsequent agreement was made after the breach of the original contract, and that the defendant having failed to perform satisfactorily which he had promised to give, remained liable on the original, contract. This case is similar to facts of the present appeal and is found to be applicable.


# 31. We find that the existing rupee term loan as well as foreign currency loan assigned by registered assignment deeds remain valid which are relevant documents to establish debt and default. We also note that the amount of default was more than Rs. 1 Crore, thus it fulfils, all the criteria laid down by the Code as well as covered under several judgments of this Appellate Tribunal as well as the Hon’ble Supreme Court of India. The argument of the Appellant that there is no debt and default, is found not sustainable. We also note that this Appellate Tribunal in its earlier order dated 24.03.2021 has already noted the fact that there has been continuous acknowledgements of the debt by the Corporate Debtor in its various balance sheets.


# 32. As regard, the subject regarding the settlement agreement stand valid or not in view of the issue raised by the Appellant regarding struck off name of the Respondent No. 1 on the relevant date, we reiterate that since the Tribunal gave clear specific verdict that the restoration would have effect as if the name was never struck off would enable the Respondent No. 1 to enforce the agreements.


# 33. The pleadings of the Appellant that the original term loan/ foreign currency loan agreement which was later assigned by the registered deed in favour of the Respondent No. 1 ceased to exist after signing the settlement agreement dated 27.08.2019 and which the Appellant choose to unilaterally terminate on 26.07.2021, by sending an e-mail to Respondent No. 1 on the plea that the name of the Respondent No 1 was struck off by the Ministry of Corporate Affairs and therefore there is no debt and default and the application filed under Section 7 of the Code could not have been allowed. We wonder, if such types of pleadings of the Appellant are to be accepted then whether any agreement would ever be honoured. Such submissions are legally not tenable and stand rejected.


# 34. Incidentally we note that the loan was sanctioned by the IDBI somewhere in 1996 and even OTS was approved by the IDBI way back in the year 2006. We also note that IDBI assigned its outstanding debts to Kotak Mahindra Bank Limited on 31.06.2006 and Kotak Mahindra further assigned the debts to Respondent No. 1 on 16.04.2008 by registered assignment deeds.


Thus, we find that the loans were sanctioned somewhere in 1996 i.e., almost 28 years back and the last assignment deed was signed in favour of the Respondent No. 1 on 16.04.2008 i.e., 16 years back and even after decades, the litigation has been continuing and no recovery could be affected by the original financial creditors or the present Respondent No. 1 in whose favour the assignment deed was signed almost 16 years back. This state of affair is found to be unusual and alarming.


# 35. In view of above detailed discussions, we find no merit in the appeal. The appeal deserved to be dismissed and stand dismissed. No Costs. Interlocutory Application(s), if any, are Closed.

---------------------------------------------


Tuesday 30 July 2024

West Bengal State Electricity Distribution Company Limited (WBSEDCL) vs. Punjab National Bank & Others - One of the necessary conditions for any transaction to be labelled as a Preferential transaction relates to the assets of the Corporate debtor, so to say that any transaction done in the relevant time by the Corporate debtor would be eligible for being called so only if done by the Corporate debtor i.e. out is its assets.

 NCLT Kolkata (2024.07.24) in West Bengal State Electricity Distribution Company Limited (WBSEDCL) vs. Punjab National Bank & Others  [I.A. (I.B.C) No. 699/KB/2023 C.P.(I.B.) No. 2179/KB/2019] held that; 

  • One of the necessary conditions for any transaction to be labelled as a Preferential transaction relates to the assets of the Corporate debtor, so to say that any transaction done in the relevant time by the Corporate debtor would be eligible for being called so only if done by the Corporate debtor i.e. out is its assets.

  • The settled position in law that emerges from the precedents of this Court is that the bank guarantee is an independent contract between bank and the beneficiary and the bank is always obliged to honour its guarantee as long as it is an unconditional and irrevocable one. The dispute between the beneficiary and the party at whose instance the bank has given the guarantee is immaterial and is of no consequence.

  • Bank Guarantees are outside the scope of the moratorium under Section 14 of the Code and Section 3 (31) specifically excludes Performance Bank Guarantees (PBGs).

  • Having regard to the ratio of the Hon’ble Apex Court in the aforenoted Judgments, and keeping in view the provisions of the Code, we are of the considered view that an irrevocable and unconditional Bank Guarantee can be invoked even during moratorium period in view of the amended provision under Section 14 (3) (b) of the Code.


Excerpts of the order;

# 1. The present application has been filed by the applicant seeking the following reliefs: 

(a)Direct the respondent bank to forthwith release payment of the amount of the Bank Guarantee bearing no. 0089ILG005612 for the sum of Rs. 3,00,00,000/- Rupees Three Crore only] in favour of the applicant, within a particular time frame; 

(b)Direct the respondent no. 4 his no objection to the payment of the Bank Guarantee amount in favour of the applicant; 

(c) Costs and incidental expenses incurred by the applicant to be borne by the respondent bank; 

(d) Such further or other order or orders be made and/or direction or directions be given as to this Hon'ble Tribunal may deem fit and proper. 


Facts of the case: 

# 2. The applicant claims that it falls within the definition of Operational Creditor as defined under Section 5(20) of the Insolvency and Bankruptcy Code, 2016 to whom the Corporate Debtor owes an operational debt arising out of non-payment of statutory electricity dues including late payment surcharge and other charges within the time frame as was agreed between WBSEB (the pre decessor-in-interest) and the Corporate Debtor by way of a Memorandum of Agreement (MoA) executed on 07.10.2004. In terms of clause 19 of the said MoA, a Bank Guarantee was executed by the Corporate Debtor as ‘Security Deposit’ in favour of the applicant which at present stood renewed at Rs.3 crore and was valid till June 17, 2023. The same is lying in custody of the Respondent No.1. 


# 3. The Corporate Debtor was admitted into CIRP vide an order dated 22.07.2022 and as a result a moratorium under Section 14 of IBC, 2016 was declared. The Corporate Debtor had not paid the electricity charges since February 2022, therefore the applicant after serving disconnection notice as mandated under Section 56 of the Electricity Act, 2003, disconnected the connection on 09.09.2022. 


# 4. The applicant states that as an amount of Rs.3,20,12,379/- became due and payable by the Corporate Debtor as on 21.07.2022, the applicant invoked the Bank Guarantee of Rs.3,00,00,000/- vide a letter dated 08.08.2022 addressed to the Respondent No.3 and requested to disburse the said Bank Guarantee within 7 (seven) days from receipt of the said letter. The Respondent No.3 on 20.08.2022 attached the communications dated 10.08.2022 and 16.08.2022 sent by the IRP and advised the applicant to take up the issue of invocation with the IRP. 


# 5. The Respondent No.2 thereafter vide a communication dated 09.09.2022 informed its inability to honour the invocation because of the advise or direction of the then IRP which was conveyed through a letter dated 18.08.2022. 


# 6. Thereafter vide an order dated 30.09.2022, this Hon’ble Tribunal appointed Mr. Avishek Gupta as the Resolution Professional on the basis of an application filed by the CoC. The Resolution Professional i.e., Respondent No.4 replied to the applicant via electronic mode on the issue of disconnection and invocation of Bank Guarantee and also forwarded the orders dated 22.07.2022 and 30.09.2022 alomgwith specimen of a requisite form and public announcement. 


# 7. The applicant on 29.11.2022 submitted its claim of Rs.3,20,12,379/- in requisite form alongwith supporting documents and the Respondent No.4 on 22.12.2022 through electronic mode and accepted the claim in full. 


# 8. The applicant again on 04.01.2023 addressed a communication to the Respondent No.3 via electronic mode to release the Bank Guarantee to which the Respondent No.2 vide a letter dated 06.01.2023 replied and refused to disburse the said Bank Guarantee by stating that as the claim of the applicant has been accepted by the RP therefore the Bank Guarantee cannot be claimed as it would amount to dual claim. 


# 9. The applicant states that this act of the Respondents is against the provision of Section 14(3)(b) of IBC, 2016. It was always communicated to the Applicant by Respondent No.4 that its claim would automatically stand reduced in case the payment is received against the bank guarantee. Therefore, the present application shall be admitted. 


# 10. Reply by the Respondents 

A. Respondent Nos.1 to 3- The contents of the Reply Affidavit filed by the Respondent Nos.1 to 3 are summarized as hereunder: 

(i) The Respondent No.1 had issued a Bank Guarantee dated 25.06.2012 for Rs.3 Crore on behalf of the Corporate Debtor for drawal of bulk supply to its premises at Hazinagar, Naihati, 24 Parganas (North) in favour of the applicant. The Respondent No.1 received the letter dated 08.08.2022 from the applicant for invoking the Bank Guarantee as the Corporate Debtor had defaulted in paying the electricity bill within time and was requested to invoke the said guarantee in full and send the outstanding payment by Pay Order/Bank Draft to be drawn in favour of the applicant. 


(ii) The Respondent No.1 received an email dated 10.08.2022 from the IRP to not allow such invocation during the period of moratorium. The IRP again made repeated requests for not invoking the guarantee by emails dated 10.08.2022 and 16.08.2022. The IRP sent a letter dated 18.08.2022 and once again requested to not invoke the Bank Guarantee in view of the moratorium as envisaged under Section 14 of IBC, 2016. The Respondent Nos. 1 to 3 informed the same to the applicant vide letter dated 20.08.2022 and requested to take up the matter with the IRP. 


(iii) That the applicant once again vide letter dated 30.08.2022 requested the Respondent Nos. 1 to 3 to encash the said guarantee but the respondent bank did not honor the same and the IRP was informed about the same vide a letter dated 09.09.2022. From the list of creditors, it is evident that the applicant already submitted its proof as an operational creditor vide Form-B dated 25.11.2022. 


(iv) The claim of the applicant has been admitted in full and it has been stated that in case any amount is recovered by invoking the bank guarantee, the same shall be informed to the RP and claim should be revised accordingly. The applicant cannot insist on encashment of the Bank Guarantee as the same will lead to double recovery. 


(v) It is also a fact that if any payment is made to the applicant during CIRP, it would tantamount to preferential treatment of the applicant over other creditors who are standing in a queue during the revival process of the Corporate Debtor. By filing its claim, the applicant has waived its right to recover from Bank Guarantee and it is also evident that the Bank Guarantee is valid upto 17th June, 2023 with claim period upto 17th June, 2024. 


(vi) The applicant once again requested to invoke the bank guarantee vide letter dated 04.01.2023 and the respondent bank vide letter dated 06.01.2023 stated that since the applicant has lodged its claim which is accepted in full by the RP, the same would amount to dual claim. 


B. Respondent No.4 

(i) The Respondent No.4/the Resolution Professional has stated in its Reply Affidavit that by Form-B dated 25.11.2022, the applicant had filed its claim before the Respondent No.4 on 29.11.2022 for a total sum of Rs.3,20,12,379/- and after consideration and verification of the same, the claim was accepted in full and was communicated to the applicant vide an email dated 22.12.2022. The Respondent No.4 further communicated that if any amount is received by the applicant by invoking the bank guarantee, the same shall be communicated to the Respondent No.4 so that the claim can be revised accordingly. 


i(ii) The Respondent No.4 also stated that the Respondent No.1 had filed its revised claim for a total sum of Rs.44,65,67,327.98/- (fund based) and Rs.4,82,47,109/- (non-fund based). The same was accepted and intimated to the Respondent No.1 vide email dated 19.01.2023. It was also informed that the non-fund-based claim was admitted under the head ‘contingent claims’. That after receiving the revised claim from the Respondent No.1, the entire fund based claim was admitted alongwith non fund based being grouped under contingent claim and accordingly the share of the Respondent No.1 was reduced to 65.86% from 67.14%. The same was discussed with the CoC members in their 11th meeting held on 30.01.2023. 


Submissions made by the Ld. Counsel on behalf of the applicant: 

# 11. The Ld. Counsel for the Applicant submitted that on a plain reading of Section 14(3)(b) of the IBC, 2016 which states that a surety in a contract of guarantee to a corporate debtor shall not apply to the working of Section 14 (1) that is Moratorium. Therefore, the initial action of working of the then IRP and the Bank in refusing to disburse the sum of Rs. 3.00 crore indisputably was not correct and in violation of the provision of Section 14 (3) (b) of the Code. 


# 12. The applicant submitted its claim/demand of Bank Guarantee amounting to Rs 3.00 crore letter dated 08/08/2022 within the validity period i.e., 17/06/2023 and claim period 17/06/2024. Therefore, in terms of the relevant clauses of the declaration dated June 25, 2012, the respondent bank is contractually and statutorily bound to release the Bank Guarantee amount in favour of the applicant. 


# 13. The Ld. Counsel further submitted that in accordance with clause no. 8 stated in the declaration dated June 25, 2012 the applicant is also entitled to receive interest on account of delayed payment to be calculated on and from August 16, 2020 till payment of the Bank Guarantee amount by the Bank. 


# 14. The Ld. Counsel also placed reliance on some judgments which are as follows: 

  • a. The National Small Industries Corporation Limited (NSCI), Delhi -versus- Sh. Prabhakar Kumar & Anr [CA(AT)(Ins) No. 841 of 2021] 

  • b. UP State Corporation -versus Sumac International Limited. [(1997) 1 SCC 568] 

  • c. U.P. Cooperative Federation Limited -versus- Singh Consultants and Engineers (P) Limited. [(1988) 1 SCC 174] 

  • d. IDBI Bank Limited -versus- Indian Oil Corporation Limited Para: 4. [CA(AT)(Ins) No. 543 of 2021] 


# 15. For the reasons stated above, the present application shall be admitted. 

Submissions on behalf of the Bank 

A counter point was raised by Ld. Counsel Ms Urmila Chakraborty, who stated that since the claimant here is also an operational creditor, he would be getting the money in excess of his claim which he has already raised before the RP and has been admitted as well. By submitting to the RP and the entire process, the applicant has now become an operational creditor and therefore having submitted himself to the process, he must stand in the Queue under section 53 of the code. There are two faces of this argument – One is of course that being an Operational Creditor he must stand in the Queue having submitted to the remedy under IBC. Now he can’t do a volte face and say that he would be encashing the Bank Guarantees. 


Analysis 

# 16. We have heard the Ld. Counsels appearing for both the parties and perused the record. 


# 17. It is the case of the applicant that the Corporate Debtor was admitted into CIRP on 22.07.2022. The applicant came to know about the same and communicated to the Respondents time and again to invoke such Bank Guarantee but the Respondents did not entertain such request stating that such Bank Guarantee cannot be invoked in view of the moratorium laid down under Section 14 of IBC, 2016. It was also stated by the Respondents that as the claim of the applicant has been admitted in full, the invocation of such Bank Guarantee would amount to a dual claim. 


# 18. An objection has been taken by the Ld. Counsel appearing for the bank that since the claimant has submitted himself to the ecosystem of insolvency as contained in the Code, having filed its claim as prescribed, he must stand in the Queue under section 53 of the code. Consequently, it shall not be entitled to encash the bank guarantee, for if that is allowed, it would amount to a preferential treatment to the applicant. We have considered this objection and here and consider it useful for the context to extract the provisions of the code in this regard: 

  • 43. Preferential transactions and relevant time. 

  • (1) Where the liquidator or the resolution professional, as the case may be, is of the opinion that the corporate debtor has at a relevant time given a preference in such transactions and in such manner as laid down in sub-section (2) to any persons as referred to in sub-section (4), he shall apply to the Adjudicating Authority for avoidance of preferential transactions and for, one or more of the orders referred to in section 44. 

  • (2) A corporate debtor shall be deemed to have given a preference, if 

  • (a) there is a transfer of property or an interest thereof of the corporate debtor for the benefit of a creditor or a surety or a guarantor for or on account of an antecedent financial debt or operational debt or other liabilities owed by the corporate debtor; and (b) the transfer under clause (a) has the effect of putting such creditor or a surety or a guarantor in a beneficial position than it would have been in the event of a distribution of assets being made in accordance with section 53. 


# 19. From the provisions above it is seen that, one of the necessary conditions for any transaction to be labelled as a Preferential transaction relates to the assets of the Corporate debtor, so to say that any transaction done in the relevant time by the Corporate debtor would be eligible for being called so only if done by the Corporate debtor i.e. out is its assets. However, since the Bank guarantee is a separate contract and the encashment thereof is not relatable to the assets of the Corporate Debtor, the encashment cannot be termed as Preferential transaction. Moreover, the said bank guarantee being a separate contract, does not come under the purview of the mechanism of Section 53. However, if encashed, the claimant shall have to revise its claim accordingly. Therefore, the contention of the Ld. Counsel for the Bank is not maintainable. 


# 20. It is also contended by the Respondents that since the Corporate Debtor was admitted into CIRP and a moratorium under Section 14 of IBC, 2016 was initiated, the applicant cannot invoke such Bank Guarantee within the moratorium period. 


# 21. In this regard, we would like to refer to Section 14(3)(b) of the Insolvency and Bankruptcy Code, 2016 which states as follows: 

  • “Section 14 (3) - The provisions of sub-section (1) shall not apply to— 

  • (a) such transactions, agreements or other arrangements as may be notified by the Central Government in consultation with any financial sector regulator or any other authority; 

  • (b) a surety in a contract of guarantee to a corporate debtor.” 


# 22. We refer to a judgment passed by the Hon’ble NCLAT, Delhi, in the matter of Bhuvan Madan v. Nominated Authority, Ministry of Coal & Anr. [Company Appeal (AT) (Insolvency) no. 989 of 2024 decided on 01.07.2024] in which it was held as follows: 

  • 18. Section 14, sub-section (3) was amended by Act 26 of 2018, w.e.f. 06.06.2018. Amendment made in sub-section (3) of Section 14 is as follows: 

  • “14(3) The provisions of sub-section (1) shall not apply to — 

  • (a) such transactions, agreements or other arrangement as may be notified by the Central Government in consultation with any financial sector regulator or any other authority; 

  • (b) a surety in a contract of guarantee to a corporate debtor. “ 

  • 19. Sub-section (3) above clearly provides that provisions of sub-section (1) shall not be applicable on a surety in a contract of guarantee to a Corporate Debtor. 

  • 20. In another judgment of this Tribunal in UCO Bank vs. Sudip Bhattacharya – Company Appeal (AT) (Insolvency) No.335 of 2021 decided on 21.09.2021, this Tribunal in paragraph 8, 9, 10 and 11 has held that Bank Guarantee cannot be held to be assets of the Corporate Debtor. 

  • 21. The learned Counsel for the Respondent has also relied on judgment of the Hon’ble Supreme Court in (2020) 13 SCC 574 – Standard Chartered Bank vs. Heavy Engineering Corporation Limited and Anr., where dealing with the precedents on the Bank Guarantee, following was held in paragraph 23: 

  • “23. The settled position in law that emerges from the precedents of this Court is that the bank guarantee is an independent contract between bank and the beneficiary and the bank is always obliged to honour its guarantee as long as it is an unconditional and irrevocable one. The dispute between the beneficiary and the party at whose instance the bank has given the guarantee is immaterial and is of no consequence. There are, however, exceptions to this rule when there is a clear case of fraud, irretrievable injustice or special equities. The Court ordinarily should not interfere with the invocation or encashment of the bank guarantee so long as the invocation is in terms of the bank guarantee.”     (emphasis applied) 


# 23. Further in the matter of IDBI Bank Ltd. v. Indian Oil Corporation Ltd. [Company Appeal (AT)(Ins) No.543 of 2021 decided on 10.01.2023], the Hon’ble NCLAT, Delhi has held as hereunder: 

  • 10. Bank Guarantees are outside the scope of the moratorium under Section 14 of the Code and Section 3 (31) specifically excludes Performance Bank Guarantees (PBGs). 

  • 11. We also find it a fit case to place reliance on the Judgment of the Hon’ble Supreme Court in the case of U.P. Cooperative Federation Ltd. vs. Singh Consultants and Engineers Pvt. Ltd. reported in [(1988 1 SCC 174] in which it is held as follows: 

  • “When irrevocable and unconditional bank guarantee payable on demand without demur then, whenever such bank guarantee is sought to be encashed by the beneficiary, bank is bound to honour the bank guarantee irrespective of any dispute raised by the customer (at whose instance the guarantee was issued) against the beneficiary” 

  • 13. Having regard to the ratio of the Hon’ble Apex Court in the aforenoted Judgments, and keeping in view the provisions of the Code, we are of the considered view that an irrevocable and unconditional Bank Guarantee can be invoked even during moratorium period in view of the amended provision under Section 14 (3) (b) of the Code. ………” 


# 24. In view of the law laid down above, we are of the view that the applicant has the right to invoke such Bank Guarantee of Rs.3,00,00,000/- and the Respondents should not come in the way of invoking the same. It shall not amount to dual claim as the amount recovered by invoking such Bank Guarantee can be adjusted and the admitted claim shall be revised accordingly. 


# 25. Therefore I.A. (I.B.C) No. 699/KB/2023 is allowed and disposed of. 


# 26. A certified copy of this order may be issued, if applied for, upon compliance with all requisites. 


---------------------------------------------


Disclaimer:

The sole purpose of this post is to create awareness on the "IBC - Case Law" and to provide synopsis of the concerned case law, must not be used as a guide for taking or recommending any action or decision. A reader must refer to the full citation of the order & do one's own research and seek professional advice if he intends to take any action or decision in the matters covered in this post.